Summary of Contents for Vickers M2-200 Series

Page 1: ...M 2700 S Revised 09 01 86 Vane Motors M2 200 M2 300 M2 400 and M2 500 Series Overhaul Manual Vickers Vane Motors...

Page 2: ...ion and Operating Instructions A Installation Drawings 6 B Drive Connections 6 C Shaft Rotation 7 D Hydraulic Tubing 7 E Hydraulic Fluid Recommendations 7 F Overload Protection 8 G Port Positions 8 V...

Page 3: ...ays include the complete unit model number as stamped on the motor cover Motors of the 13 design will be referred to in the discussion which follows in Sections II through VII but information is essen...

Page 4: ...s The vanes slide radially in the rotor slots to follow the cam contour of the ring Rocker arms hold the vanes out against the ring The rotor is splined to the output shaft The shaft is sup ported by...

Page 5: ...cated on vane 9 As any two successive vanes pass the A and A1 slots fluid between them is trapped and carried to the B and B1 slots Here the distance between the rotor and ring is decreasing and the f...

Page 6: ...i higher than system pressure is obtained by placing a 30 psi check valve between the pump and directional valve and sampling pressure ahead of the check valve see Figure 5 S2 Connection No Shuttle Va...

Page 7: ...passed pump tests similar to those used in developing the antiwear type hydraulic oils b Meet the viscosity recommendations shown in Table 3 This table summarizes oil types recommended for use with V...

Page 8: ...he system and or by proper filtration of the air 5 Proper oil filling and servicing of filters breathers reservoirs etc cannot be overemphasized 6 Good system and reservoir design will insure that aer...

Page 9: ...otor Make certain sufficient hydraulic fluid is available to the motor Check motor drive speed System overload relief valve set too low Check pressure and reset relief valve Motor requiring excessive...

Page 10: ...ain the seal is firmly in place and is not cocked Press the outer bearing onto the shaft while supporting the inner race Cover the shaft splines with tape or a bullet and install the shaft The outer b...

Page 11: ...mbly View M2 500 Series Only Screw Flange O ring Washer not used on M2 200 series Cover O ring Wave Washer Pressure Plate O ring Ring Pin Screw Screw Flange O ring M2 500 Series Only Vane Rotor Sub as...

Page 12: ...Ring Overpass Holes Added Pins Relocated Overpass Holes Added Figure 8 Change from 12 to 13 Design Series Nomencl t re Design Series Nomencl t re Design Series Nomenclature 11 12 13 Series Nomenclatu...

Page 13: ...ation 0000 All rights reserved Printed in U S A Eaton Hydraulics 15151 Highway 5 Eden Prairie MN 55344 Telephone 612 937 7254 Fax 612 937 7130 www eatonhydraulics com 46 New Lane Havant Hampshire PO9...