7. SIDE PANEL  

Removal of side panel 

1.  Unlock the side panel with the key supplied (Fig 1). 

2.  Tilt the panel to clear the upper flange. 

3.  Lift the panel upwards to clear two locating pins (Fig 2). 

 

     Reinstall side panel 

1.  Align the two holes on the bottom of the side panel with the two pins on the enclosure 

frame. (Fig 2) 

2.  Then lower the side panel on to the pins.   

3.  Lock the side panel with the key supplied (Fig 1). 

Summary of Contents for REC Series

Page 1: ...1 2015 Eaton Corporation All rights reserved REC Series Enclosure Installation Guide _issue 4 Installation Guide REC Series Rack Installation Guide...

Page 2: ...4 Installation Guide REC Series Rack Installation Guide TABLE OF CONTENTS SECTION SAFETY WARNINGS 1 600 WIDE EXPLODED VIEW 2 800 WIDE EXPLODED VIEW 3 SWITCHING DOOR HANDING 4 STABILIZING 5 BAYING THE...

Page 3: ...equipment may cause the enclosure to tip over 4 WARNING First load the heaviest electronic devices and accessories into the bottom of the enclosure to prevent the enclosure from becoming top heavy 5...

Page 4: ...rporation All rights reserved REC Series Enclosure Installation Guide _issue 4 2 600 WIDE EXPLODED VIEW Installation Guide ITEM DESCRIPTION 1 Vented Door Assembly Option 2 Enclosure Frame 3 Roof Panel...

Page 5: ...allation Guide _issue 4 Installation Guide 3 800 WIDE EXPLODED VIEW 5 6 6 ITEM DESCRIPTION 1 Vented Door Assembly Option 2 Double Vented Door Assembly Option 3 Enclosure Frame 4 Vented Door Assembly O...

Page 6: ...tall the three hinge sections to the opposite side of enclosure frame Fig 2 4 Rotate the door 180 degrees 5 Re install the three hinge pins Fig 1 6 Loosen the two screws which secure the locking rods...

Page 7: ...MPLEMENTED AND THE RACK MUST REMAIN STATIC IF THE RACK IS TO BE RELOCATED THEN EQUIPMENT MUST BE REMOVED BEFORE MOVING THE RACK Each enclosure is equipped with four leveling feet Fig 1 Use a 13 mm spa...

Page 8: ...sure Fig 1 2 Position and level the adjacent enclosure frames Ensure that the frames are precisely aligned both vertically and front to back 3 Ensure a shake proof washer contacts the painted surface...

Page 9: ...he side panel with the key supplied Fig 1 2 Tilt the panel to clear the upper flange 3 Lift the panel upwards to clear two locating pins Fig 2 Reinstall side panel 1 Align the two holes on the bottom...

Page 10: ...osure Installation Guide _issue 4 Installation Guide 8 RACK MOUNT ADJUSTMENT 1 Loosen the four bolts using a 5mm Allen key do not remove the bolt Fig 1 2 Slide rails to desired location 3 Ensuring the...

Page 11: ...ts note not all components used in every application ITEM REF DESCRIPTION LENGTH QUANTITY IMAGE 1 M6 x 25mm Zinc Plated Setscrew 25mm 4 2 M6 Shake proof Washer 8 3 M6 x 12mm Setscrew 4mm Allen 12mm 4...

Page 12: ...itions M6 Thread forming screw M6 Shake proof washer Earth grounded cage nut M6 Shake proof washer M6 Thread forming screw The bolt together method for the rack frame ensures earth continuity of the r...

Page 13: ...th bonding points to corner gussets adjacent to door hinge positions If double doors are fitted then fit main earth points to both adjacent corner gussets Note Main earthing points must be assembled s...

Page 14: ...k STEP 3 19 INCH RAIL EARTH BONDING Remove the side panel to improve access Fit earth assembly as shown in Fig 3 0 and tighten assembly using a torque of M6 Plain washers X2 M6 Serrated hex flange M6...

Page 15: ...the RH side panel to the rear corner gusset M6 Plain washers X2 M6 Serrated hex flange nut M6 Earth lead 350mm To doors Fig 6 0 M6 Plain washers X2 M6 Earth lead 500mm Fig 5 0 STEP 5 EARTH BONDING TO...

Page 16: ...aisle shown for reference Fitting instructions follow same process but 1800mm wide aisles have wider side and roof panels TOOLS REQUIRED SPANNER WRENCH 8mm SPANNER WRENCH 10mm ALLEN KEY 5mm CROSS HEA...

Page 17: ...served REC Series Enclosure Installation Guide _issue 4 Installation Guide Step 1 Ensure cabinets are aligned level and the correct distance apart either 1200mm or 1800mm depending on the aisle config...

Page 18: ...mage right 13 12 Doors viewed from inside Master Door Slave Door 7 1 2 3 4 5 6 8 7 9 9 10 11 ITEM DESCRIPTION QTY 1 FRAME UPRIGHT LEFT 1 2 FRAME UPRIGHT RIGHT 1 3 CROSS BEAM 1 4 TOP PANEL 42U 1 5 TOP...

Page 19: ...hown 10 12 Step 4 Fit the hinges item 9 to the frame uprights items 1 2 using M5 x 8mm screws item 10 shown in image below Note the hinges are handed Left or Right Fit hinges to corresponding door 42U...

Page 20: ...L DOOR FRAME Installation Guide Step 6 Referring to images below offer up door frame to cabinets and attach using clamp plates item 11 and M6 x 16mm screws item 7 from inside the cabinets in 4 positio...

Page 21: ...e frame and lifting them onto the hinge pins Note the door positions and panel gaps can be adjusted by loosening the hinge fixing screws and altering their relative positions The gap between the door...

Page 22: ...aster door to be opened from inside the aisle To open the door from inside the aisle pull button while lifting latch refer to images below and push master door to the open position STEP 1 PULL Release...

Page 23: ...ation visit www eaton eu electrical Eaton Industries Manufacturing GmbH Electrical Sector EMEA Route de la Longeraie 7 1110 Morges Switzerland Copyright 2012 All rights reserved Changes to the product...

Reviews: