INSTALLATION
Eaton 9910 UPS and EBM Installation Guide (6000 VA Models)
S
P-164000007 Rev 1
32
6.
To set the time and date, configure the UPS for an installed EBM,
or change other factory-set defaults, see “Operation” on page 35.
7.
If you installed an optional REPO switch, verify that the function is
working correctly by performing the following tests:
S
Activate the external REPO switch. Verify that the status
changes on the UPS are displayed.
S
Deactivate the external REPO switch and restart the UPS.
8.
Charge the batteries. With load, the internal batteries charge to
90% capacity in less than 8 hours. However, you must charge the
batteries for 48 hours after installation or long-term storage.
9.
Connect the devices that you want to protect to the applicable UPS
output receptacles.
Do not turn on the devices.
For information about
using load segments, see “Load Segments” on page 38.
NOTE
Do not protect laser printers with the UPS because of the exceptionally high power
requirements of the heating elements.
10.
To prevent a UPS overload condition, turn on one connected device
at a time and verify that each device starts up completely before
turning on the next device.
11.
To install a communication option, see “Communication Features”
on page 37.