Eaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual 164000639—Rev 03
35
11. Secure the positive, negative, and ground DC power wiring to the wire tie anchors (see
) using
Zip ties.
NOTE
If installing more than one IBC–SW, individual conduit will be run between each battery
cabinet and the UPS or disconnect.
DO NOT
run battery wiring from subsequent IBC–
SWs through the bottom of the adjacent IBC–SWs.
12. If installing more than one IBC–SW, repeat
Steps 2
through
11
for each IBC–SW, and then proceed to
paragraph
Installing IBC–SW Interface Wiring
; otherwise, proceed to paragraph
Installing IBC–SW Interface Wiring
NOTE
The internal battery string is to be connected by an authorized Eaton Customer Service
Engineer at system startup.
13.
Bottom Entry Wiring.
Remove the bottom conduit plate (see
) from the inside bottom of the
IBC–SW. Identify all conduit requirements and mark their location. Drill and punch all conduit holes in the
bottom conduit plate prior to mounting on the IBC–SW. Install the conduit plate and install all conduit runs
into the plate. Pull the wiring through the conduit into the wiring areas.
Note:
Power and Interface wiring share the same conduit plate.
14. Route the battery wiring (positive and negative) from the UPS DC Input terminals or DC disconnect tie
point through the bottom of the IBC–SW to the wiring channel on the left side of the IBC–SW (see
). Route the wiring along the wiring channel to the IBC–SW DC Output terminal block. See
for terminal locations. See paragraph
IBC–SW Power Wiring Preparation
and
for
wiring requirements. Refer to the applicable Eaton 93PM UPS Installation and Operation manual listed in
paragraph
, for UPS cabinet terminal locations.
15. Secure the battery wiring to the wire tie anchors (see
) using Zip ties.
16. Route the battery cabinet ground wiring from the UPS through the bottom of the IBC–SW to the IBC–SW
ground terminal block. See
for terminal location. See paragraph
IBC–SW Power Wiring Preparation
and
for wiring requirements.
17. Connect the positive and negative power wiring to the IBC–SW DC (
+
) and DC (
–
) output terminals.
Connect the ground wiring to the ground terminal on the IBC–SW. See paragraph
IBC–SW Power Wiring Preparation
and
for termination requirements.
For a detailed view of the IBC–SW terminal block, see .
18. Connect the positive, negative, and ground DC power wiring from the IBC–SW or disconnect to the UPS
cabinet battery and ground terminals. Refer to the applicable Eaton 93PM UPS Installation and Operation
manual listed in paragraph
, for UPS cabinet termination requirements.
19. Secure the positive, negative, and ground DC power wiring to the wire tie anchors (see
) using
Zip ties.
NOTE
If installing more than one IBC–SW, individual conduit will be run between each battery
cabinet and the UPS or disconnect. DO NOT run battery wiring from subsequent IBC–
SWs through the bottom of the adjacent IBC–SWs.
20. If installing more than one IBC–SW, repeat
Steps 13
through
19
for each IBC–SW, and then proceed to
paragraph
Installing IBC–SW Interface Wiring
; otherwise, proceed to paragraph
Installing IBC–SW Interface Wiring
NOTE
The internal battery string is to be connected by an authorized Eaton Customer Service
Engineer at system startup.