26
Eaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual 164000639—Rev 03
CAUTION
To prevent tipping when rolling the cabinet, push the cabinet from the rear whenever possible.
16. Roll the IBC–SW to the line-up-and-match installation location on the side of the UPS cabinet making sure
the covers are flush with each other or to the standalone installation location.
17. Lower the cabinet’s leveling feet and using a bubble level, adjust the leveling feet accordingly until the
cabinet is level.
18. Locate the top splice bracket shipped with the IBC.
19. Remove the screws along each adjacent cabinet top panel securing the top panels. Retain the hardware
for later use.
20. Install the top splice bracket between the adjacent cabinet and secure the tie strap with retained hardware.
21. If permanently mounting the IBC (requires the optional Floor Mount Bracket Kit), continue to
Step 22
;
otherwise, proceed to
Step 25
.
22. Locate the two floor mounting brackets from the Floor Mount Bracket kit.
23. Using the retained cabinet mounting bolts, install the floor mounting brackets to the front and rear of the
IBC with the angle facing outward.
24. Secure the cabinet to the floor with customer-supplied hardware.
NOTE
In standalone configurations, multiple IBCs are installed adjacent to each other, but
separate from the UPS.
25. If installing more than one IBC, remove the rectangular knockouts on the bottom front sides the IBCs (see
) and repeat
Steps 1
through
24
; otherwise, proceed to
Step 26
.
Install additional IBCs on the right or left side of the first IBC.
26. Proceed to paragraph
.
Summary of Contents for IBC-SW
Page 68: ...16400063903 164000639 03...