GridAdvisor™ Series II smart sensor installation instructions

IL915001EN

April 2019

Eaton.com

9

Reed switch functionality 

Reed switch functionality

The smart sensor’s internal Reed switch and a magnet are 
used to trigger the following functions:

Bluetooth functionality

Over-the-air (OTA) commissioning

Factory reset

The primary selection of the menu occurs when the first valid 
Reed switch operation is detected. Once this is detected, the 
cell radio is shutdown.

During shutdown, the LEDs will do a very fast blue blink, 
after that a 10 second window is opened and the LEDs flash 
the color associated with a menu option. 

If another valid switch is detected the next menu item is 
displayed. If a switch is 

not

 detected, the lights will go solid 

indicating that a selection was made. 

Once the reed switch is activated, the actions detailed in 
Table 3 occur.

Support

Eaton is proud to offer a comprehensive collection of support 
resources for users requiring additional information or 
assistance in the setup, operation, and troubleshooting of 
GridAdvisor Series II smart sensor and other equipment from 
Eaton. 

For technical support, contact EAS Support at 800-815-2258 
or [email protected], or contact your local Eaton 
representative.

Table 3. Reed switch function sequencing

Sequence steps

Action

LED Behavior

First reed switch activation

After 10 seconds, if no further reed switch closure occurred, 
the Bluetooth radio will be turned on, enter discoverable 
mode and wait for a connection.

Load and Source LEDs will flash a simultaneous blue sequence.
After 10 seconds, the Load and Source LEDs will light solid for 2 
seconds indicating that Bluetooth functionality is active. 
You may now initiate Bluetooth pairing. 

Second reed switch activation

After 10 seconds, if no further reed switch closure occurred, 
a request to run OTASP on the next modem power up will be 
selected.

Load and Source LEDs will flash a simultaneous yellow sequence.

Third reed switch activation

After 10 seconds, if no further reed switch closure occurred, 
the option to reset the sensor to factory default settings is 
selected and the sensor will wait another 10 seconds for 
an additional, fourth activation to confirm the factory reset. 

Note:

 This is the only reed switch selection that must be 

confirmed with an additional reed switch activation to 
initiate the factory reset.

Load and Source LEDs will flash a simultaneous red sequence.

Load and Source LEDs will flash a simultaneous 

fast

 red sequence 

while waiting for the factory reset confirmation.

Upon confirmation, the Load and Source LEDs will light solid for 2 
seconds and the factory reset occurs.

Fourth reed switch activation

No action is taken and the sensor exits the reed switch menu.

Load and Source LEDs will turn off.

Summary of Contents for GridAdvisor II Series

Page 1: ...IL915001EN GridAdvisor Series II smart sensor installation instructions Effective April 2019 Supersedes August 2017 Energy Automation Solutions ...

Page 2: ...SHALL NOT BECOME PART OF OR MODIFY ANY SUCH PRIOR OR EXISTING AGREEMENT The information recommendations descriptions and safety notations are based on Eaton experience and judgment THIS INFORMATION SHOULD NOT BE CONSIDERED AS ALL INCLUSIVE OR COVERING ALL CONTINGENCIES If further information is required Eaton should be consulted In no event will Eaton be responsible to the user in contract in tort...

Page 3: ...lampstick hotstick etc Following is important safety information For safe installation and operation of this equipment read and follow all cautions and instructions This manual may contain four types of hazard statements Indicates a hazardous situation which if not avoided will result in death or serious injury Indicates a hazardous situation which if not avoided could result in death or serious i...

Page 4: ...ile a claim with the carrier immediately Handling Be careful during handling and storage of the sensor to minimize the possibility of damage If the sensor is to be stored for any length of time prior to installation provide a clean dry storage area Quality standards ISO 9001 certified quality management system Installation procedures SIM cards A SIM card is a small removable card consisting of an ...

Page 5: ...disconnect of ProView NXG software 5 OTASP may take up to five 5 minutes with included retries so do not the remove battery from the sensor within this time frame 6 OTASP results can be confirmed in the sensor s communication logs with the ProView NXG software Note If the OTASP process fails and the sensor blinks red LEDs continuously check the communication log for diagnostics OTASP can fail if s...

Page 6: ... The exact trip value is dependent on the overall diameter of the double back neutral wires Figure 2 Recommended methods of concentric neutral primary cable preparation Method 2 refer to Figure 2B 1 Attach one or two strands of the concentric neutral wrapped around the cable to the tie off tab on the elbow 2 Terminate all of the remaining neutral wires just below the elbow The balance of the neutr...

Page 7: ...a location shown in Figure 4 while holding the hotstick horizontal The triggering mechanism will release the clamping arms and securely attach the device to the cable Note Only the closed core current transformer CT need be applied over the region of the cable where the concentric neutral has been removed or double backed Figure 5 For installation on tape shield cable the closed core CT of the sen...

Page 8: ...e annunciation during the installation of device to verify proper load current is present Programming sensor Refer to the GridAdvisor Series II Smart Sensor ProView NXG software programming manual MN915003EN for instructions on connecting to the sensor with the Bluetooth module and or programming device with ProView NXG software Load LED Source LED Table 1 GridAdvisor Series II Smart Sensor LEDs P...

Page 9: ...uence steps Action LED Behavior First reed switch activation After 10 seconds if no further reed switch closure occurred the Bluetooth radio will be turned on enter discoverable mode and wait for a connection Load and Source LEDs will flash a simultaneous blue sequence After 10 seconds the Load and Source LEDs will light solid for 2 seconds indicating that Bluetooth functionality is active You may...

Page 10: ...eived including interference that may cause undesired operation Anatel Anatel homologation 3670 15 8433 01 07898994273486 GridAdvisor Model E0013X41G10 Este equipamento opera em caráter secundário isto é não tem direito a proteção contra interferência prejudicial mesmo de estações do mesmo tipo e não pode causar interferência a sistemas operando em caráter primário This equipment operates on a sec...

Page 11: ...GridAdvisor Series II smart sensor installation instructions IL915001EN April 2019 Eaton com 11 Regulatory information ...

Page 12: ...utomation Solutions Division 3033 Campus Drive Suite 350N Minneapolis MN 55441 United States Eaton com 2019 Eaton All Rights Reserved Printed in USA Publication No IL915001EN Rev 3 April 2019 Eaton is a registered trademark All other trademarks are property of their respective owners For GridAdvisor series II smart sensor product information call 1 877 277 4636 or visit Eaton com ...

Reviews: