7. COMMISSIONING
Verify that all prior check-boxes in this document are ticked and that each section is signed-off. If not,
return this document to the relevant persons, asking them to complete the relevant section(s) of the form.
Do not proceed with the commissioning process begin until ALL previous details have been
checked and signed-off.
Failure to observe this warning may result in unsatisfactory performance,
personal injury and potential damage to equipment.
F
Obtain approval for commissioning from the relevant persons or authority. In some areas, a
representative from the energy authority must inspect and approve the installation prior to
commissioning. Check your local laws.
F
Double-check that load circuits are isolated.
F
Measure the supply voltage with a meter to ensure that it is present at the correct voltage,
especially if a generator or temporary supply is to be used for commissioning. Operation at out-of-
tolerance voltages may cause faulty operation or damage the unit.
F
If testing with a generator supply, ensure that the generator neutral line is earthed at the point of
connection to the building. Do not rely upon a temporary generator earth.
F
Reset circuit breakers/fuses on supply switchboard and remove danger tag.
F
Operate the master switch, if applicable.
Power should now be applied to the unit.
F
After a short period (<5 seconds), there should be a blue indicator visible through the window on
the door panel.
Be aware of any sources of heat, burning smells or unusual noises. It is normal for this type of
unit to emit a faint buzzing sound from the filter components inside the unit. If any problems arise,
shut down the supply immediately, isolate and inspect. If in doubt, contact Eaton for information
before proceeding.
NOTE! If a red indicator is visible on the front panel, this indicates a fault condition. Contact Eaton
or your distributor for information.
F
Proceed to commission the load. Remove any tags fitted and operate the applicable load breakers
on the load switchboard.
F
Following the recommended practices, start-up the load equipment and ensure it operates
correctly. If possible, operate the load equipment in all possible conditions, continuing the period of
testing until correct operation has been determined.
After load equipment is turned on, be aware of any sources of heat, burning smells or unusual
noises. It is normal for the unit to emit a faint buzzing sound from the filter unit, which may
become louder or softer, depending on the applied load. If any problems arise, shut down the
supply immediately, isolate and inspect. If in doubt, contact Eaton for information before
proceeding.
F
Shut down load equipment and isolate load breakers (if it is not desired to leave equipment
operating afterward).
This completes commissioning. Please sign-off and proceed to the next section.
Completed by:
Date: