23

Instruction Book    

IB182942EN   July 2018   www.eaton.com

DST-2-VR

+

VR-Series

+

 Replacement Circuit Breaker

Figurt 5.4. DST-2-7.5-VR

+

 in Conntct Position

g.  (Domestic Version)  In the “test” position, the breaker can be 

operated manually and electrically, thus allowing maintenance 

tests or checks. To operate the breaker electrically, the secondary 

control block must be engaged at this time. The slider is located 

on the lower right hand area of the circuit breaker frame. If 

electrical testing is desired at this stage, engage the secondary 

control block slider by releasing the slide latch and pushing 

the slider toward the rear several inches. Push firmly on the 

front side of the slider until the contact block engages with the 

corresponding cell receptacle. Return the manual motor cutoff 

switch to the “on” position. The spring charging motor will begin 

to run and charge the closing spring. The breaker is now in 

the “test” position, with control voltage applied, and ready for 

electrical or manual testing.

g.  (Canadian Version)  In the test position, the breaker can be 

operated manually and electrically, thus allowing maintenance 

tests or checks. To operate the breaker electrically, the secondary 

block must be engaged. On Canadian versions, the secondary 

block for 250Vdc versions is located on the lower, rear, center of 

the breaker. Other Canadian versions, the secondary disconnect 

operates in a manner similar to the domestic US models detailed 

above. The secondary block automatically engages in the test 

position. Return the manual motor cut-off switch to the “on” 

position. The spring charging motor will begin to run and charge 

the closing springs. The breaker is now in the “test” position, with 

control voltage applied, and ready for manual or electrical testing. 

(* For DST-2-7.5-VR

+

 with centered secondary disconnect block)

h.  To install the breaker in the connected position the levering 

handle will have to be used. Insure the breaker is open and 

engage the levering handle with the breaker and floor levering 

cutouts. (See Figure 5.5)

i.  Depress the Interlock Pedal and start levering in the breaker by 

shifting the levering handle back and forth. Once movement has 

started, the pedal should be released. The closing springs may be 

in the charged state but the internal PS switch will open circuit 

the close spring release coil  (preventing an electrical close). 

At this point any attempt to mechanically close the breaker will 

cause a trip-free operation with no recharging of the closing 

springs  (PS2 has open-circuited the charging motor circuit and 

the Interlock Pedal operation has automatically turned the motor 

cutoff switch to “off”). As advancement into the cell continues, 

the primary voltage source shutters will open allowing the breaker 

stabs to engage with the source.

j.  Continue moving the breaker into the cell using the levering 

handle from the test position until a mechanical stop is reached. 

This is the fully engaged or connected position. The connect 

position can be verified by the inability to move the breaker 

in or out, the Interlock Pedal is up and has released the trip 

mechanism, and the cell label “operating” is visible on the floor of 

the cell in front of the breaker’s left front wheel. Manually return 

the motor cutoff switch to the “on” position. The breaker is now 

ready for service.

5.10.3   REMOVAL PROCEDURE (LEVERING-IN VERSION)

To remove the breaker from the cell it must be in the open position. 

Insure the breaker is open and engage the levering handle. 

The Interlock Pedal must be depressed which will raise the trip 

mechanism and trip the breaker. Move the breaker out using the 

levering handle illustrated in Figure 5.5. The breaker will start coming 

out of the cell before the main stabs are disconnected and will be in 

a non-operable mode and will go through a trip-free operation if any 

attempt to close it is made in the intermediate position. Also, the 

secondary control block will disengage automatically before the main 

stabs are disconnected. 

otte:

N

(Canadian Version)  The secondary block will remain connected until the 

breaker is removed from the test position.

The shutters will close after the main stabs have cleared, isolating 

the breaker from its source. Continue levering out until the position 

indicator on the floor of the cell shows test and the Interlock Pedal 

rises to lock the breaker in position. At this time you are in the test 

d.  Push the circuit breaker into the cell until all the wheels are on 

the guide rails and the spring discharge linkage has not cycled. 

(For Canadian breakers, the interlock plunger will rest in the 

first cell position.)  No mechanical stop will be reached. This is 

the “disconnect” position and the breaker can still be operated 

because there is no interface of the cell floor interlocks with 

breaker interlock linkage. No cell labeling is provided to verify this 

position. 

e.  Depress the pedal and push or lever the breaker further into the 

cell. (Figure 5.3) 

otte:

N

Depressing of the Interlock Pedal automatically positions the motor 

cutoff switch to “off”.

f.  Once movement has started, the Interlock Pedal should be 

released if depressed. The levering handle may be required to 

move the breaker completely into the test position and its use is 

illustrated in Figure 5.3. An audible click of the interlock plunger 

engaging the interlock rail will be observed when moving from 

the disconnect position. The Interlock Pedal will travel down at 

the beginning of movement and rapidly rise to lock the breaker in 

the test position at the end of the normal travel from disconnect 

to test. The movement of the handle provides an open signal 

that remains throughout all intermediate breaker positions and 

the floor trip will be combined with a closing signal between the 

disconnect and test position to discharge the closing springs. 

The breaker remains in the trip-free state until the test position is 

reached. The test position can be verified by the inability to move 

the breaker in or out, the Interlock Pedal is in the up position, and 

the cell label “test” is visible on the floor of the cell in front of the 

breaker’s left front wheel.

Summary of Contents for DST-2-VR+ Series

Page 1: ...Instruction Book IB182942EN DST 2 VR VR Series Replacement Circuit Breaker DST 2 VR 250 2000A Shown July 2018 Supersedes March 2018 Effective...

Page 2: ...ions of this equipment do not purport to be covered by these instructions If further information is desired by purchaser regarding his particular installation operation or maintenance of particular eq...

Page 3: ...ERATION CHECK 21 5 4 VACUUM INTERRUPTER INTEGRITY 21 5 5 LOW FREQUENCY WITHSTAND TEST INSULATION CHECK 21 5 6 CONTACT EROSION AND WIPE 21 5 7 PRIMARY CIRCUIT RESISTANCE 21 5 8 ELECTRICAL OPERATIONS CH...

Page 4: ...portant that this installation and maintenance instruction booklet be read and followed closely to achieve optimum performance and a long useful circuit breaker life in its application 1 1 VISUAL INST...

Page 5: ...Latching Momentary Capabilities kV MVA Amps K Low Freq kV RMS Impulse kV Peak I kA RMS KI kA RMS kA RMS Peak DST 2 7 5 500 DST 2 7 5 VR 500 8 25 500 1200 2000 1 25 36 95 33 41 66 111 DST 2 15 500 DST...

Page 6: ...on com DST 2 VR VR Series Replacement Circuit Breaker Table 2 DST 2 VR Dimensions Circuit Breaker Type Existing Circuit Breaker Rated Continuous Current at 60 Hz Amps A B C D E F DST 2 VR 1200 2000 65...

Page 7: ...est coupler engaged Failure to disconnect the test coupler could result in an electrical shock leading to death severe personal injury equipment damage and or improper operation Do not work on a close...

Page 8: ...and other components If damaged or loss is detected file claims immediately with the carrier and notify an Eaton representative Tools and Accessories Maintenance Tool Style 94C9506G01 This tool is us...

Page 9: ...ition before placing it in to storage The circuit breaker is shipped with its contacts open and closing springs discharged The indicators on the front cover should confirm this Insert the end of the m...

Page 10: ...w of DST 2 VR Front External View 1 Lock Out Tag Out 5 Manual Charging Socket 9 Push To Close Button 2 Levering In Access 6 Spring Charged Discharged Indicator 10 Interlock Pedal 3 Handle 7 Operations...

Page 11: ...T 2 VR VR Series Replacement Circuit Breaker Figure 3 3 b Rear External View of DST 2 VR Rear External View 1 Lifting Points 4 Anti Rotation Self Adjuster Optional 2 Secondary Disconnects 5 Ground Con...

Page 12: ...t is assembled at the factory as a unit to assure correct dimensional relationships between working components Three interrupter assemblies are used per circuit breaker Each vacuum interrupter assembl...

Page 13: ...ER CONTACTS ARE CLOSED OR THE CLOSING SPRINGS ARE CHARGED THE CIRCUIT BREAKER CONTACTS MAY OPEN OR THE CLOSING SPRINGS DISCHARGE CAUSING CRUSHING INJURY DISCHARGE THE SPRINGS AND OPEN THE CIRCUIT BREA...

Page 14: ...This is the anti pump function 4 4 1 TIMING The opening and closing times for the circuit breakers vary depending upon the control voltage power rating environment and test equipment Differences in ti...

Page 15: ...est and Connect positions OPERATION C and NO C and NC C and NO C and NO C and NC C and NO Brown Switch Black Switch Black Switch Brown Switch SWITCH TERMINAL LS1 bb LS2 aa LS2 bb LC PS1 PS2 Circuit Br...

Page 16: ...ring system tripping and spring release interlocks perform the following a Set the breaker mechanically trip free during the first 4 inches of travel into the cell and whenever the breaker receives a...

Page 17: ...Cover Removed VR Series Circuit Breaker Element Mechanism 1 LH Closing Spring 5 Spring Release Assembly 9 Manual Charge Socket 2 Latch Check Switch To Rear of Motor Cutoff Switch 6 Shunt Trip Assembly...

Page 18: ...eaker Closed Springs Charged 2 1 3 4 5 6 7 8 9 10 11 12 13 14 Closing Cam and Trip Linkage 1 Spring Release Close Latch 6 Ratchet Wheel 11 Anti Close Interlock 2 Pole Shaft 7 Spring Crank 12 Motor Rat...

Page 19: ...2 Main Link 6 Cam Shaft 10 Trip Latch Reset Spring 3 Operating Rod 7 Banana Link 11 Shunt Trip Lever 4 Pole Shaft 8 Trip latch 12 Shunt Trip Coil 4 1 2 3 5 6 7 8 9 10 11 12 4 8 a Circuit Breaker Open...

Page 20: ...a cell containing an MOC until after the switch has been properly adjusted WARNING MEASUREMENTS AND ADJUSTMENTS SHOULD NEVER BE ATTEMPTED IN AN ENERGIZED STRUCTURE IF THE STRUCTURE CANNOT BE DE ENERGI...

Page 21: ...YS REMOVE THE MAINTENANCE TOOL AFTER CHARGING THE SPRING FAILURE TO REMOVE THE MAINTENANCE TOOL FROM THE BREAKER COULD CAUSE INJURY TO PERSONNEL AND OR EQUIPMENT DAMAGE IF THE BREAKER WAS TO CLOSE Clo...

Page 22: ...n The test position can be verified by the inability to move the breaker in or out the Interlock Pedal is in the up position and the cell label test is visible on the floor of the cell in front of the...

Page 23: ...onnect position can be verified by the inability to move the breaker in or out the Interlock Pedal is up and has released the trip mechanism and the cell label operating is visible on the floor of the...

Page 24: ...s DISCHARGED and that the main contact status indicator reads OPEN Manually trip close and trip the breaker as needed to obtain this status Note N The motor cutoff switch is located on the lower cover...

Page 25: ...so that the circuit breaker could be closed It must be returned to the fully withdrawn condition prior to insertion in the circuit breaker compartment b From the withdrawn position align the center g...

Page 26: ...al of the circuit breaker Note N For Canadian versions with separate disconnect and test positions it will stop at the test position Electrical and mechanical tests of the circuit breaker can be perfo...

Page 27: ...and retest or replace Insulation Integrity Main circuit to ground Withstand 15kV 60Hz for 1 Minute 5kV Rating Hi pot Tester Clean and retest or replace Control circuit to ground Charging Motor discon...

Page 28: ...ommended that the equipment be capable of delivering 25 milliamperes for one minute The current delivery capability of 25 mA ac applies when all three vacuum interrupters are tested in parallel If ind...

Page 29: ...ressed in micro ohms Repeat for the remaining two poles The resistance should not exceed the factory test levels more than 200 as stated in IEEE C37 09 Factory test levels are recorded on the circuit...

Page 30: ...ol Mounting Testing Locations by Circuit Breaker Type CIRCUIT BREAKER DESIGNATION APPROXIMATE MECHANISM CHASSIS WIDTH INCH LOWER MOUNTING HOLE LOWER MOUNTING HOLE MARKER PLACEMENT HOLE VR Series 18 A1...

Page 31: ...a sheet of paper that can be kept as a record of the test Record the date of the test person conducting the test circuit breaker serial number and the operations counter on the tape or paper Figures 6...

Page 32: ...Marker Interface Cam Marker CloSure Tool TM 15 O 15 O Figure 6 13 Determining the Distance Traveled Figure 6 14 Illustrative Testing Tape Sample Figure 6 12 Evaluate the CloSure Performance Date of Br...

Page 33: ...nt requires maintenance only once every ten years or ten thousand operations which ever comes first After a ten year service interval or when ten thousand operations have been reached contact your loc...

Page 34: ...urned Motor Cut Off Contacts open or burned Trip Coil Assembly Clapper fails to reset Closing sound but no close Pole Shaft Not open fully Trip Latch Reset Spring Damaged or missing Trip Bar D Shaft F...

Page 35: ...SWITCH Circuit Breaker Auxiliary Switch 94C9525G13 5 POSITION SWITCH Circuit Breaker Position Switch PS1 94C9525H06 6 POSITION SWITCH Circuit Breaker Position Switch PS2 94C9525H07 7 LATCH CHECK SWITC...

Page 36: ...ulevard Cleveland OH 44122 United States Eaton com 2018 Eaton All Rights Reserved Printed in USA Publication No IB182942EN July 2018 Eaton is a registered trademark All trademarks are property of thei...