Preventative maintenance instructions

If any issues are found regarding the below, contact PS-WarrantyServices@

Eaton.com for assistance on transformers under warranty. Additionally, these 

reports must be available upon request to maintain warranty period.

Transformer Exterior Maintenance

Items to Inspect

Points to be Checked

Remedial Action

Frequency

Exterior Surfaces

Inspect for evidence of tampering, battered metal, 

gouges, etc. Check for any damage that would 

allow the entrance of wires or other metallic 

devices.

Any such damage should be repaired 

immediately.

Annual

Paint or Protective Coatings

Inspect for scratches or weathering.

Any such damage should be touched up 

immediately. 

Annual

Tank Leaks

Check tank exterior for signs of a leak.

Any such leaks should be repaired immediately. Annual

General Location

Check the area around the transformer for stored 

tools, materials, equipment or debris.

Anything on or against the transformer should 

be removed.

Annual

General Location

Walk completely around unit and listen for 

abnormal noises; should be a steady hum without 

intermittent rattling

Any such abnormal noises should be reported 

and investigated.

Annual

Pad

Verify that pad has not tilted resulting in a 

transformer that is more than 5° from horizontal.

If pad support is compromised or out of level 

greater than 5°, repair it immediately.

Annual

Nameplates

Abnormal or unexpected fading of nameplates or 

decals.  

Contact your Eaton representative for 

replacement nameplates and decals as 

necessary.

Annual

Unusual Odors

Smells of fluid or burning. This could be indicative 

of an unseen leak under the base. Also, inspect the 

concrete around the perimeter of the transformer 

base for oil spotting.

Any such abnormal odors should be reported 

and investigated.

Annual

Cabinet Interior Maintenance

Items to Inspect

Points to be checked

Remedial Action

Frequency

Gauges and Controls

Check for proper operation. 

Repair or replace damaged or defective 

equipment.

Annual

Equipment Leaks

Inspect drain cocks, plugs, fuse mountings, and 

switches. Look for evidence of insulating liquid 

seepage around tank-wall gaskets, seals, etc.

Repair as required. Replacement of gaskets or 

seals in the tank wall may require that the tank 

be opened and the insulating liquid lowered 

to the appropriate level. For instruction on 

opening the tank and for draining and replacing 

the insulating liquid, refer to the 

Insulating 

Liquid Maintenance

 section.

Annual

Tank Pressure

Check that pressure/vacuum gauge does not 

remain at zero for an extended period of time. It 

is preferable that a given unit not cycle between 

negative and positive pressures on a daily basis. 

Commissioning pressures have been documented 

in a separate paper based on the top fluid 

temperature. Any observed readings lower than -2 

psig or greater than +7 psig indicate a condition 

that can and should be corrected.

If the pressure/vacuum gauge remains at zero 

for an extended period of time this may be 

evidence of air leakage in and out of the tank. 

A leak test should be performed by adding 

nitrogen to the airspace and observing for loss 

of pressure over an interval of a minimum of 

12 hours. If the pressure is lost, locate the leak 

and repair immediately.

Annual

WARNING

Hazardous voltage . Can cause severe injury, death, or 

damage to equipment . De-energize transformer from 

a remote upstream source before opening cabinet 

and doing cabinet interior inspection or maintenance . 

Check that all transformer terminals and bushings have 

zero voltage . Ground transformer following industry 

accepted safe grounding practices .

16

SubStation tranSformer inStallation and partS replacement information

   MN202002EN   JUNE 2016

Summary of Contents for COOPER POWER SERIES

Page 1: ...transformer installation operation and maintenance instructions and parts replacement information COOPER POWER SERIES Effective June 2016 Supersedes S210 15 10 February 2013 Substation Transformers M...

Page 2: ...ISTING CONTRACT BETWEEN THE PARTIES ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON THE CONTENTS OF THIS DOCUMENT SHALL NOT BECOME PART OF OR MODIFY ANY CONTRACT BETWEEN THE PARTIES In no even...

Page 3: ...ling fans 6 High voltage bushings 7 Low voltage bushings 7 De energized tap changer 8 Insulating liquid 8 Vacuum fault interrupter VFI 9 Maintenance 11 Periodic inspection 11 Removing and replacing bu...

Page 4: ...information DANGER Hazardous voltage Contact with hazardous voltage will cause death or severe personal injury Follow all locally approved safety procedures when working around high and low voltage l...

Page 5: ...ection to detect any signs of damage or mishandling Locate any accessory parts that may have been shipped separately 3 If any damage is detected or shortages are noticed write a brief description on t...

Page 6: ...t make any connections except as authorized by the nameplate or schematic Improper connections can result in severe personal injury and damage to the equipment Transformers equipped with an internal t...

Page 7: ...which could lead to failure of the transformer caution Before breaking the seal of any handhole manhole or bushing hole bleed internal pressure to zero Seals should not be broken in the presence of f...

Page 8: ...indicate the top liquid temperature in the tank in degrees Centigrade The temperature sensitive element is mounted in a leak proof well permitting removal of the thermometer without lower ing the oil...

Page 9: ...and contact ratings refer to the schematic furnished with the transformer When required the pressure gauge is furnished with a pressure regulator that will automatically regulate the tank pressure be...

Page 10: ...mer windings All contacts are factory set to operate at the temperatures shown in the connection diagram If readjustment of the contacts is desired consult the factory for detailed instruction Transfo...

Page 11: ...is through the manhole When reinstalling the bushing install a new gasket in the gasket recess on the underside of the flange to insure that the gasket is properly seated in the groove A flat washer...

Page 12: ...late Insulating liquid The insulating liquid in substation transformers is either conventional transformer oil R Temp fluid or Envirotemp FR3 fluid When makeup liquid is required use only approved flu...

Page 13: ...equipment Do not operate loadbreak equipment if a fault condition is suspected Doing so can cause an explosion or fire Use a hotstick to operate transformer loadbreak equipment After operating transfo...

Page 14: ...iated Refer to Service Information S285 75 1 Tri Phase TPG and TPG with SCADA Electronic Control Installation and Operation Instructions for electronic control operation instructions Standard electric...

Page 15: ...working with bushings make sure that the transformer is de energized and that all circuits to and from the transformer are grounded in order to discharge any stored energy and prevent accidental re e...

Page 16: ...hing for removal 5 Remove the bushing Replacing Replacement bushings can be installed by following the removal procedure in reverse order Clamp bolts should be tightened as specified in Table 1 The ga...

Page 17: ...ctions from the tank flange noting the location and orientation up down of each piece To reinstall the bolt on main tank cover 1 Return the gasket sections to their original positions and orientation...

Page 18: ...R3 fluid can be filtered by means of a filter press The filter press is effective for removing all types of foreign matter including finely divided carbon and small amounts of moisture The purifier eq...

Page 19: ...at lower temperatures If the transformer cover or manhole must be removed for internal service exposure time to ambient air should be minimal Avoid exposure times greater than 24 hours Immediately aft...

Page 20: ...hould be reported and investigated Annual Cabinet Interior Maintenance Items to Inspect Points to be checked Remedial Action Frequency Gauges and Controls Check for proper operation Repair or replace...

Page 21: ...in plating will achieve a rainbow coloring if a particular terminal is experiencing an over temperature condition Tighten any loose connections immediately Any damage or discoloration that is observed...

Page 22: ...This page is intentionally left blank 18 Substation transformer installation and parts replacement information MN202002EN JUNE 2016...

Page 23: ...This page is intentionally left blank 19 Substation transformer installation and parts replacement information MN202002EN JUNE 2016...

Page 24: ...call 1 877 277 4636 or visit www eaton com cooperpowerseries SAFETY FOR LIFE Eaton 1000 Eaton Boulevard Cleveland OH 44122 United States Eaton com Eaton s Power Systems Division 2300 Badger Drive Wau...