6.4.2 Starting the Parallel UPS in Bypass Mode
If the inverter output of the parallel UPS is not available and the critical load needs to be energized:
CAUTION
In Bypass mode, the critical load is not protected from commercial power
interruptions and abnormalities.
1.
Unfasten the front door by lifting the latch from the bottom and turning to the right
(counterclockwise) and swing the door open (Figure 6-1).
2.
Verify that all input breaker are open.
3.
Verify that the Maintenance bypass switches are open.
4.
Close all Module Output Breakers (MOBs).
5.
Close all UPS input feeder circuit breakers.
6.
If the UPSs are wired for dual input, close all of the UPS Bypass input feeder circuit breakers.
7.
Close all input breakers.
8.
If the UPSs are wired for dual input, close all of the bypass input switches.
9.
Make sure MBS cover is installed.
10. Close the door and secure the latch.
11.
Close the external battery breakers.
11.
Observe the UPS control panel display becoming active, indicating logic power.
12. Verify no alarms are active.
13. Select the CONTROLS symbol on the main menu bar. The System Control screen is displayed.
14. If not already selected, select UPS on the System Control screen.
15. On the UPS System Control screen, select the LOAD OFF
BYPASS command, then press the
RETURN
pushbutton.
The critical load is immediately supplied by the bypass source, in Bypass mode from
all UPSs. The BYPASS status indicator is illuminated.
68
Eaton 93E
MK2
UPS (10-40kVA, 380/400/415V) Installation and Operation
Summary of Contents for 93E MK2
Page 1: ...Eaton 93E MK2 UPS 10 40 kVA 380 400 415V Installation and Operation Manual...
Page 2: ......
Page 4: ......
Page 8: ......
Page 49: ...Notes 39 Eaton 93E MK2 UPS 10 40kVA 380 400 415V Installation and Operation...
Page 94: ......
Page 95: ......
Page 96: ...614 00389 00...