5.2
Steps to install the UPS
Power and control wiring are routed through the rear of the cabinet with
connections made to easily accessible terminals, see
Figure 16: Gland plate and
connector locations in the 15-20 kW standard and C-model frames
and
Figure
17: Gland plate and connector locations in the 30-40 kW frame
To install and connect the power cabling of the external battery to the UPS, see
Section 5.3 Battery system installation
.
Figure 16: Gland plate and connector locations in the 15-20 kW standard and C-
model frames
1. Connectors
2. Gland plate
Figure 17: Gland plate and connector locations in the 30-40 kW frame
1. Connectors
2. Gland plate