ICC / ICU SYSTEM INSTALLATION MANUAL
January2005: E\Manuals\Others\Qualitair\ICC\0412115B
5
3. LOCATION & MOUNTING OF INDOOR UNIT (ICC)
←
→
ICC 25
ICC 35
ICC 50
ICC 60
ICC 70
A
475 475 475 525 525
B
390 390 390 440 440
C
805 805 805 865 865
D
450 450 450 525 525
E
680 680 680 740 740
F
680 680 680 680 680
G
62 62 62 92 92
H
62 62 62 32 32
J
300 300 300 350 350
K
50 50 50 50 50
Figure 3.2 – ICC Positioning
3.1 Location
The ICC unit should be mounted level on a load bearing wall or ceiling. The minimum distance from
the floor should be 1.8 metres to ensure good air convection. The side inlet grilles should have a
minimum clearance from obstruction of 100mm and the minimum clearance in front of the unit should
be 1.5 metres.
3.2 Fixing
The unit should be fixed to the wall using two-off rear fixings (1) or to the ceiling using the two-off
top fixings (2). 10mm diameter rawbolt type fixings (supplied by others) with large steel washers are
recommended for fixing to a local load bearing wall or ceiling. Locking screw holes to be used to
prevent equipment moving once installed.
3.3 Service
Connections
The refrigerant pipe connections are accessed through the left hand side panel (3). Cable entry is on
the right hand side of the unit. A plastic drain connector is supplied (inside the control box) to be site
fitted onto the condensate tray.
SPECIAL NOTE
ENSURE THE INDOOR UNIT IS INSTALLED LEVEL TO PREVENT DRAINAGE PROBLEMS.