13. FINAL CHECKS
Check
1)
Have all options kits been fitted ?
2)
Have units been mounted level and correct drainage been checked by pouring 2 litres
of water into drip tray?
3)
Has the ICU (outdoor) drain been connected, if required?
4)
Have the suction line and condensate drains been adequately insulated?
5)
Has the correct HRC external fusing / isolating been installed?
6)
Has additional extended pipe-run refrigerant charge been measured into the system,
where necessary?
7)
Has the indoor condensate drain been trapped ?
8)
Is there adequate room and access to remove the access panels ?
9)
Has the control system been explained to the customer and the operating manual sheet
handed over with the appropriate sections completed?
10)
Has the warranty booklet been read and completed? Note:- If a service contract is not
taken out only a 1-year warranty is applicable.