1-1  PURPOSE  OF  LOAD  BANK:  The  LB-60-30  is  a  portable  load  bank  designed  to  be  used  for  field 
servicing and testing 60HZ generators and UPS systems. It can be used for checking cables after they 
have  been  replaced  or  repaired.  The  load  bank  can  also  be  shipped  to  different  locations  using  the 
carrying case. 

 

1-2  RATING OF LOAD BANK: The LB-60-30 is rated at 30 KW full loads with all six load steps turned 
on. The load steps are 1KW, 2KW, 2KW, 5KW, 10KW and10KW. This gives a 0-30KW range in 1KW 
steps.  All steps are continuous. 

 

1-3  LOAD  BANK  DESCRIPTION:  The  load  bank  is  completely  self-contained  and  needs  no  power 
source to operate other than the power being tested. The different sides of the load bank are shown in 
fig. 1-1. The air enters the right side (fan side) and exits the left side. 

 
 
 
 
 

 

<<<< AIR FLOW <<<< 

 
 
 
 
 
 
 

 

LEFT SIDE------------- 

---------      RIGHT SIDE (FAN SIDE) 

 
 
 
 
 
 
 
 
 
 
 
 

FIGURE 1-1 

LENGTH 

20 IN. 

WIDTH 

8 IN. 

HEIGHT 

11 IN. 

WEIGH  33 LBS. 

Summary of Contents for LB-60-30

Page 1: ...gle Eye Power Solutions LLC LB 60 30 LOAD BANK MANUAL CONTAINS OPERATING INSTRUCTIONS PARTS LIST WIRING DIAGRAMS SERVICE INSTRUCTIONS Eagle Eye Power Solutions LLC 4031 W Kiehnau Ave Milwaukee WI 5320...

Page 2: ...THE POTENTIAL OF DELIVERING A LETHAL SHOCK THIS LOAD BANK SHOULD BE USED ONLY BY TRAINED AND QUALIFIED PERSONNEL THIS LOAD BANK IS DESIGNED FOR TEMPORARY USE ONLY THE LOAD RESISTORS ARE ENERGIZED WHEN...

Page 3: ...GLE PHASE 2 1 TESTING 240VAC SINGLE PHASE 2 3 TESTING 208VAC THREE PHASE 2 5 PARTS PARTS INFORMATION 3 1 CONTROL PANEL PARTS LAYOUT FIGURE 3 1 3 2 CONTROL PANEL PARTS LIST 3 3 INTERIOR PARTS LAYOUT FI...

Page 4: ...LOAD BANK The LB 60 30 is rated at 30 KW full loads with all six load steps turned on The load steps are 1KW 2KW 2KW 5KW 10KW and10KW This gives a 0 30KW range in 1KW steps All steps are continuous 1...

Page 5: ...C VOLTS AC AMPS FREQUENCY METER METER SWITCH 60 58 55 HERTZ A B C 62 65 L1 L2 L3 B A C ON MAIN POWER INDICATOR LIGHTS OFF METER RATE SWITCHES METER TEST JACKS 1KW 2KW 2KW 5KW 10KW 10KW OFF A B C N FIG...

Page 6: ...equency of the power unit It should read approximately 60HZ METER SWITCH Switch used to select A B or C phase on the voltmeter RATE SWITCHES Switch used to select the desired rate on the load bank The...

Page 7: ...of the power unit 2 3 CHECKING THE POWER check the following A The amber light A should beon B The voltmeter should read 120VAC on A phase C The frequency meter should read approximately60HZ D The amm...

Page 8: ...t of the power unit 2 3 CHECKING THE POWER check the following A The amber light A and B should beon B The voltmeter should read 120VAC on A and B phase C The frequency meter should read approximately...

Page 9: ...2 3 CHECKING THE POWER check the following A The amber light A B C should beon B The voltmeter should read 120VAC on A B and C phase C The frequency meter should read approximately60HZ D The ammeter...

Page 10: ...LC PARTS INFORMATION CONTROL PANEL PARTS 1 11 2 60 90 30 0 120 150 40 60 20 0 80 100 AC VOLTS AC AMPS 4 55 3 60 58 HERTZ A B C 62 65 L1 L2 L3 B 10 A C 5 6 7 METER MAIN ON 9 OFF 1KW 2KW 2KW 5KW 10KW 10...

Page 11: ...BER USED 1 MR 61 0 150V VOLT METER 1 2 MR 64 0 100 A AMMETER 1 3 MR 60 55 65 HERTZ FREQUENCY METER 1 4 HD 25 HANDLE 2 5 KN 10 POINTER KNOB 1 6 SW 13 ROTARY SWITCH 3POSITION 1 POLE 1 7 SW 21 TOGGLE SWI...

Page 12: ...INTERIOR PARTS LAYOUT 4 3 15 1 2 5 8 23 21 23 22 24 25 19 6 16 17 18 20 9 10 7 7 11 12 13 14 FIGURE 3 2...

Page 13: ...5 RELAY 120VAC 30A 6 8 RC 25 560 RESISTOR 5W 1 9 RC 56 5 6K RESISTOR 5W 1 10 RY 20 RELAY 2PDT 24VDC 3A 1 11 SW 11 AIR FLOW SWITCH 1 12 RS 20 RELAY SOCKET 2P 1 13 LR 08 8 0 RESISTOR 15 14 LR 40 40 RESI...

Page 14: ...Eagle Eye Power Solutions LLC FAN PANEL PARTS LAYOUT 10 1 2 3 4 5 6 7 8 9 FIGURE 3 3...

Page 15: ...STOR 25W 3 2 TM 20 8 POSITION TERMINAL STRIP V BEAU PRODUCTS 78008 1 3 TM 10 TERMINAL STRIP 11 POS 1 4 RD 06 RECTIFIER 6A 1 5 CP 35 CAPICATOR 350UF 160VDC 1 6 FP 28 ALUM FAN PANEL 1 7 GL 10 FAN GRILL...

Page 16: ...be kept free of any trash Do not place any objects in the fan or resistor grill FAN REPLACEMENT The following are steps to take to replace a defective fan 1 Remove the screws holding the fan panel to...

Page 17: ...1 WIRES TO LOAD BANK FAN PANEL WIRING FIGURE 5 2 1 RED 6 BLK 4 G R ED F1 F1 F2 F2 F3 8 G B LU F3 3 4 G RE D F4 F4 F5 9 WHT 10 WHT F5 F6 7 8 G BL U F6 F1 F2 F3 C1 9 WH ITE SW11 12 WHITE 7 11 RED R5 1R...

Page 18: ...Eagle Eye Power Solutions LLC INTERIOR WIRING...

Page 19: ...K3 SW5 2KW K4 SW6 5KW K5 SW7 10KW K6 D1 4 DIODE 1A D5 ZENER DIODE 120V5W FN1 6 FAN 24VDC FS1 FUSE 5A FS2 FUSE 1A FS3 5 FUSE 125A K1 6 RELAY 120VAC 3PST 30A K7 RELAY 24VDC 2PDT3A L1 3 LIGHT NEON 115V...

Page 20: ...gle Eye Power Solutions LLC Contact EEPS Eagle Eye Power Solutions LLC 4031 W Kiehnau Ave Milwaukee WI 53209 TEL 1 877 805 EEPS 3377 FAX 1 414 962 3660 www eepowersolutions com info eepowersolutions c...