PowerDepot H5B series User Manual
10
3.1.5 Engineering coordination
Attention should be paid to the following items before construction:
Power cable specification.
The power cable specification shall meet the requirements of maximum discharge
current for each product.
Mounting space and bearing capacity.
Make sure that the battery has enough space to install, and that the battery rack
and bracket have enough load capacity.
Wiring.
Make sure the power cable and ground wire are reasonable. Not easy to
short-circuit, water and corrosion.
3.2 Equipment installation
The wall for battery installation shall be solid brick or cement wall with strong bearing capacity
and wall thickness no less than 100mm.
Mounting space requirements
:
Floor installation
Wall installation
If the battery is installed indoors, please leave a certain gap during installation according to the
picture above, ventilation is required, combustible materials should not be placed around the
battery.
Table 3-2 Installation steps
Step1
System outage
1. Ensure that the battery is in a shutdown state
(Disconnect the battery power cable and press the Reset
button to turn it off)