Assembled Cable Bundle Ready for Pulling

17. 

To pull the cable bundle through the conduit, tie a suitable cord through the Pull Loop on 
the sleeve.  Then, from the other side of the conduit, gently pull the cord.  If resistance is 
encountered, gradually increase the pulling force.  If the cable bundle will not move with 
moderate pulling force, STOP pulling and pull the cable back from the other side.  Please 
examine the fill in the conduit and remove any obstructions, then try pulling the cable bundle 
again.  Cable lubricant may also be used to assist with pulling, and is recommended for 
difficult cable runs.

NOTE:

 NECA standards for cable runs specify that conduit should be not more than 40% full, 

and should have not more than two 90 degree bends per pull.  The performance of this Pull 

Sleeve Kit may be degraded if these standards are exceeded.

18. 

Once the cable bundle has been pulled, inspect the Pull Sleeve for any signs or damage.  If 
there are signs of damage on the sleeve, note the location and inspect further in this area 
once the Pull Sleeve has been disassembled. 

19. 

To disassemble the assembled Pull Sleeve, follow the assembly instructions above in 
reverse. 

NOTE

:  The use of knives for disassembly is NOT recommended, as they may damage the cables 

in the bundle.

DVIGear

1059 Triad Court, Suite 8
Marietta, GA USA 30062
Toll Free: 

888.463.9927 

Tel: +1.770.421.6699 
Fax: +1.770.234.4207
[email protected] 
www.dvigear.com

DVI-2600-AOC-PSK-QSG-02 / August.2020

© 2020 DVIGear, Inc.

DVIGear, Inc. is the owner of numerous trademarks, both registered and unregistered, 
including without limitation, the following marks:  DVIGEAR

®

, DISPLAYNET

®

DISPLAYNET SERVER

®

, DISPLAYNET MANAGER

®

, N/AV Design

®

, and HYPERLIGHT

®

.

All other third party trademarks used herein are the properties of their respective owners.

Summary of Contents for DVI-2600-AOC-PSK

Page 1: ...it Contents The HyperLight Pull Sleeve Kit consists of the following components HyperLight Pull Sleeve HyperLight Cable Pull Cover p n DVI 2600 AOC CVR x 2 The installer will need to provide the follo...

Page 2: ...d around the cable s to be pulled and serves as a strength member that protects the cable s from undue tension The Flexible Sleeving 3 covers and protects the cable bundle from getting snagged on cond...

Page 3: ...pull it away from the exposed Pull Cord 5 Pull the sleeve back until the Pull Cord is fully exposed as shown below 6 Attach the covered connectors to the Pull Cord Starting at the side closest to the...

Page 4: ...nd not to other AOC cables in the bundle When finished the taped connectors should look like this 8 Wrap the excess Pull Cord around the bundle of cables The two ends of the Pull Cord must be wrapped...

Page 5: ...there is around 4 5 inches of pulling cord left 11 Form a termination knot with the remaining Pull Cord in order to maintain tension when pulling the bundle Start by grabbing both ends of the cord 12...

Page 6: ...the braids on the sides of the cable as shown below 15 The Pull Sleeve is now ready to go over the cable bundle Push the sleeve back over the bundle of cables If there are issues getting the sleeve t...

Page 7: ...nd right before the termination knot at the end of the Pull Cord 16 Finally wrap electrical tape around the end of the Pull Sleeve and the termination knot at the end of the Pull Cord as shown below O...

Page 8: ...Kit may be degraded if these standards are exceeded 18 Once the cable bundle has been pulled inspect the Pull Sleeve for any signs or damage If there are signs of damage on the sleeve note the locatio...