68
Section D - Configuration, cont’d.
Two Rooftop Air Conditioners with Heat Strip Plus One
Furnace
To configure two rooftop air conditioners with heat strip
plus one gas furnace,
ZONES
need to be established. For
explanation purposes the front air conditioner will be ZONE
1 and the rear air conditioner will be ZONE 2. ZONES can
be arranged per the customer’s wishes.
EACH unit must have AC power connected to it. DC power
and the communications line from the Comfort Control
Center is only connected to one unit control box.
A second communications line must be connected between
the two units’ control boxes.
Two (2) furnace thermostat wires must be routed to ONE
unit.
For explanation purposes the 12V DC, Comfort Control
Center communications line and the two (2) furnace ther-
mostat wires are to ZONE 1 (front) unit.
FIG. D27
ZONE 1
configuration should have Dip switch 1 (heat
strip) to ON position and all other Dip switches to OFF
position. The cold (freeze) control should be plugged
into P5 (blue) connector on the AC power module.
FIG. D28
C
OMMUNICATIONS
LINE
Manual
Compliments
of
Northwest
RV
Supply
Printed
From
http://www.nwrvsupply.com