Complete all of the following prior to installing the boiler.

Codes

This boiler product is a gas-fired, direct vent, condensing boiler and 

must be installed to conform to the requirements of the authority 

having jursidiction or, in the absence of such requirements:
United States - National Fuel Gas Code (NFPA-54/ANSI Z223.1).
Canada - National Gas and Propane Installation Code, Can/CSA 

B149.1.

Where required by the authority having jurisdiction, the installation 

must conform to the American Society of Mechanical Engineers 

Safety Code for Controls and Safety Devices for Automatically Fired 

Boilers, No.CSD-1.

NOTICE

Important - In the state of Massachusetts 

this product must be installed by a licensed 

plumber or gas fitter and the installation must 

be in accordance with 248 cMR

.

Installers

 - Follow local regulations with respect to installation of 

CO (Carbon Monoxide) Detectors. Follow maintenance recommen-

dations in this manual.

Installation Requirements Specific To The State Of 

Massachusetts For Direct Vent, Mechanical Vent, And 

Domestic Hot Water Appliances

For all side wall horizontally vented gas fueled equipment installed 

in every dwelling, building or structure used in whole or in part 

for residential purposes, including those owned or operated by the 

commonwealth and where the side wall exhaust vent termination is 

less than seven (7) feet above finished grade in the area of the vent-

ing, including but not limited to decks and porches, the following 

requirements shall be satisfied:

Installation of carbon monoxide detectors: at the time of instal-

1. 

lation of the side wall horizontal vented gas fueled equipment, 

the installing plumber or gasfitter shall observe that a hard 

wired carbon monoxide detector with an alarm and battery 

back-up is installed on the floor level where the gas equipment 

is to be installed. In addition, the installing plumber or gasfitter 

shall observe that a battery operated or hard wired carbon mon-

oxide detector with an alarm is installed on each additional level 

of the dwelling, building or structure served by the side wall 

horizontal vented gas fueled equipment. It shall be the respon-

sibility of the property owner to secure the services of qualified 

licensed professionals for the installation of hard wired carbon 

monoxide detectors.

Read the entire installation manual before beginning the instal-

1. 

lation. Failure to follow these rules for safe installation and 

operation and these instructions could cause a malfunction 

of the boiler and result in death, serious bodily injury, and/or 

property damage.
Check all applicable state and local building codes and util-

2. 

ity company requirements before installation. The installation 

must conform with these requirements in their entirety. In the 

absence of these codes, use NFPA Installation Codes and good 

industry practice.
Before servicing the boiler - allow the boiler to cool. Always 

3. 

shut off any electricity and gas supply connected to the boiler 

prior to servicing.
Inspect gas line for leaks.

4. 

Be certain gas input rate is correct. Over firing may result in 

5. 

early failure of the boiler sections. This may cause dangerous 

operation. Under firing may result in too much air for the pre-

mix burner causing poor or loss of combustion.
Never vent the products of combustion from this boiler to an 

6. 

enclosed space. Always vent to the outdoors. Never vent to 

another room or to inside a building.
Be sure there is adequate outdoor air supply to boiler for com-

7. 

plete combustion.

Follow a regular service and maintenance schedule for efficient 

8. 

and safe operation. 
Keep boiler area clean of debris and free of combustible and 

9. 

flammable materials.
Proper through the wall or through the roof combustion vent-

10. 

ing shall be in accordance with the materials and methods 

described in this manual. Installation must comply with local 

codes.
This boiler and related hot water heating systems are not do it 

11. 

yourself items. They must be installed and serviced by qualified 

professionals.

rules for safe insTallaTion and operaTion

before insTalling THe boiler

!

  

WARNING

This boiler has been equipped for residential 

installations. If used for commercial 

applications, any additional code requirements 

must be adhered to for installation. This may 

require additional controls including but not 

limited to a low water cut off, a manual reset 

high temperature limit, and wiring and/or 

piping modifications. The manufacturer is not 

responsible for any field installation changes 

made to a boiler installation which are not 

described or acknowledged in this manual.

Summary of Contents for 90-100

Page 1: ...D DIRECT VENT CONDENSING HOT WATER BOILER INSTALLATION OPERATION MAINTENANCE MANUAL An ISO 9001 2008 Certified Company DUNKIRK BOILERS 85 Middle Rd Dunkirk NY 14048 www dunkirk com P N 14683301 Rev C...

Page 2: ...d all instructions carefully before starting the installation Save this manual for reference WARNING Improper installation adjustment alteration service or maintenance can cause injury or property dam...

Page 3: ...es information which should be followed to ensure proper installation and operation H Warnings and Safety Symbols 3 Introduction 4 Boiler Ratings Capacities 5 Boilers For Use At High Altitude 6 Rules...

Page 4: ...reduced CO and NOx emissions which contribute to a cleaner and healthier environment This appliance unlike normal residential atmospheric and induced draft units takes its combustion air directly fro...

Page 5: ...t of this heat is available to heat water A small portion is heat from the jacket and surfaces of the boiler and it is assumed that this heat stays in the structure The Net I B R Rating represents the...

Page 6: ...boilers with the exception of the 90 75 LP product are factory equipped for operation at altitudes ranging from 0 10 000 feet above sea level No changes to the factory settings are required for instal...

Page 7: ...331096 For model 90 75 LP units only at altitudes above 5 000 ft install 90 75 High Altitude Orifice Kit 550001810 For all other alti tudes use factory installed orifice Series 90 100 Stock Factory Bt...

Page 8: ...the services of qualified licensed professionals for the installation of hard wired carbon monoxide detectors Read the entire installation manual before beginning the instal 1 lation Failure to follow...

Page 9: ...ed hot water heating systems See the table BOILER RATINGS AND CAPACITIES page 5 of this document Heat loss calculations should be based on approved industry meth ods Considerations For Boiler Location...

Page 10: ...clearances BEFORE INSTALLING THE BOILER CAUTION Keep boiler area clean of debris and free of flamable and combustible materials vapors and liquids WARNING When vent pipe is exposed to temperatures be...

Page 11: ...oors and windows 3 and all doors between the space in which the appliances remain ing connected to the common venting system are located and other spaces of the building Turn on clothes dryer and any...

Page 12: ...ply and return piping from top access The boiler unit can also be piped from the left side by turning the supply elbow and from the rear of the unit by removing plugs in the rear boiler section Near B...

Page 13: ...13 Figure 3 Multi zone Boiler Piping With Zone Valves Near Boiler Piping...

Page 14: ...circulators the furnished circulator pump should be used as one of the zone pumps Each stripped end of the electrical wires for the circulator pump inside the junction box should be taped or wire nut...

Page 15: ...content Boiler contains 2 6 gallons U S Size expansion tank accordingly Consult expansion tank manufacturer for proper sizing information Connect properly sized expansion tank not furnished as shown i...

Page 16: ...16 Figure 6 Diaphragm Type Expansion Tank Piping Near Boiler Piping...

Page 17: ...17 Figure 7 Conventional closed type Expansion Tank Piping Near Boiler Piping...

Page 18: ...to remove condensate to a drain line sanitary line above boiler if a floor drain is not available or its in accessible Figure 8 Condensate Drain Piping Near Boiler Piping Filling Condensate Trap With...

Page 19: ...on boiler are sized 3 for 2 pipe Any pipe size change to 3 must be made outside of the boiler casing in a vertical run of pipe to allow for proper drainage of vent condensate Due to potential for flu...

Page 20: ...d Locate or guard the vent to prevent accidental contact with people or pets Terminate the vent above normal snowline Avoid locations where snow may drift and block the vent Ice or snow may cause the...

Page 21: ...istance of 15ft 9 5m Vent shall not terminate within 3 ft 900mm of a window or door that can be opened in any building or any non mechanical air supply inlet to any building or of the combustion air i...

Page 22: ...Wall Vent Intake terminations Less Than 12 Clearance Above Grade Figure 10B Side Wall Vent Intake Terminations 12 Or More Clearance Above Grade Combustion Air and Vent Pipe Less Than 12 Clearance 12...

Page 23: ...23 Figure 11 Combustion Air and Vent Piping Combustion Air and Vent Pipe...

Page 24: ...ent 9 will be visible around perimeter of a properly made joint Handle pipe joint carefully until cement sets 10 Support combustion air and vent piping a minimum of 11 every 5 feet using pre formed me...

Page 25: ...ipe 5 8 3 4 1 2 3 4 20 131 000 216 000 189 000 393 000 40 90 000 145 000 129 000 267 000 60 72 000 121 000 103 000 217 000 Outside diameter Gas Supply Piping Checking The Gas Piping The boiler and its...

Page 26: ...adian Electrical Code Part 1 CSA C22 1 Electrical Code Run a 14 gauge or heavier copper wire from the boiler to a grounded connection in the service panel or a properly driven and electrically grounde...

Page 27: ...27 Figure 13 Field Wiring Connections Electrical Wiring...

Page 28: ...LLOW G GREEN R RED V VIOLET BR BROWN PUR PUPPLE 24 VOLT WIRING 24 VOLT FIELD WIRING 120 VOLT WIRING 120 VOLT FIELD WIRING INDUCER GAS VALVE BLOWER TEMPERATURE SAFETY SWITCH DIFFERRENTIAL AIR PRESSURE...

Page 29: ...PPER DIFFERENTIAL AIR P3 9 HIGH LIMIT MANUAL RESET PRESSURE SWITCH 4 5 1 3 VR8205A P12 1 P12 2 LOCATION OF CONNECTOR PLUG BETWEEN SCHEMATIC AND BLK WHT AND THE UNIT RECEPTACLE IS LIVE WHEN CAUTION ON...

Page 30: ...fferential The differential can be adjusted with the white Differential Adjustment Wheel on the aquastat and gives the flexibility for boiler operation The larger the differential the longer the run c...

Page 31: ...f there is no place for the water to expand its volume i e a properly sized and properly functioning expansion tank pressure on the inside of the boiler and heating system will increase The furnished...

Page 32: ...re outside the stated ranges Cleaning the Hydronic System IMPORTANT Do not mix different manufacturers products Doing so will void the warranty of the boiler Consideration MUST be given to cleaning th...

Page 33: ...r Suppliers Recommended Products Interstate Chemical 2797 Freedland Road P O Box 1600 Hermitage PA 16148 0600 www interstatechemical com Tel 800 422 2436 Fax 724 981 8383 Intercool NFP 30 40 50 AA Int...

Page 34: ...e Repeat step 2 for all remaining zones 3 Open the expansion tank service valve and the tank vent Fill 4 the tank to the proper level and close the tank vent Remove the handle from the expansion tank...

Page 35: ...l for gas 7 including near the floor If you smell gas STOP Follow B in the safety information above on this label If you don t smell gas go on to next step Turn the gas control knob counterclockwise 8...

Page 36: ...ting 2 Volt power is being supplied to the inte grated control A B C m D m E m Thermostat calls for heat energizing system circulator A l B m C m D m E m Integrated boiler control goes through self ch...

Page 37: ...es in dicating the hot surface igniter is powered for the 20 second igniter warm up period The bright yellow orange glow of the hot surface igniter can be observed through the observation port in the...

Page 38: ...sured input rate should be within 2 of the input rating 8 from step 2 If within 2 go to step 9 If not adjustment is required proceed as follows Turn boiler off A Set up U tube manometer or differentia...

Page 39: ...KNOB PRESSURE REGULATOR ADJUSTMENT UNDER CAP SCREW INLET PRESSURE TAP VR8205 WIRING TERMINALS 2 OUTLET PRESSURE TAP Figure 17 Manifold Pressure Measurement Detail Figure 18 Gas Valve Check Out Procedu...

Page 40: ...____ Installation instructions have been followed Checkout procedure and adjustments performed Maintenance and Service issues reviewed with owner maintenance person Installation booklet affixed on or...

Page 41: ...ses Check the air baffle located inside 1 x 2 flexible coupling on the mixer clean it if necessary and make sure to put it back Refer to repair parts diagram of mixer and pressure switch assembly for...

Page 42: ...ower to boiler at service 1 switch Close manual gas valve to turn off gas supply to boiler NOTICE The following service procedures must be performed only by a qualified service agency Boiler owner sho...

Page 43: ...ough C the condensate lines to thoroughly flush out any sediment or debris in the lines Reinstall and connect the condensate trap using the hose D clamps to secure the various condensate lines to thei...

Page 44: ...44 Service Hints Detailed Sequence Of Operation...

Page 45: ...or heat or turning the service switch off and back on or b waiting for the control to automatically reset after 15 minutes for loss of combustion airflow or one hour for loss of flame Draft Inducer Te...

Page 46: ...ENDS CALL FOR HEAT GAS VALVE AND CIRCULATOR PUMP ARE DE ENERGIZED AND FLAME LIGHTS GO OUT BLOWER RUNS FOR 30 SECONDS POST PURGE PURGE LIGHT IS ON BLOWER IS DE ENERGIZED FOR 30 SECONDS PURGE LIGHT SHUT...

Page 47: ...it is being damaged by some other problem an electrical short burning out a transformer for example Initial Service Checks Before troubleshooting 1 Make sure that circuit breaker is on or fuse is ok...

Page 48: ...OWERED OR AIR FLOW IS NOT PROVEN OFF DURING IGNITER AND RUN CYCLE NORMAL OPERATION PURGE CYCLE COMPLETE BLINKING IBC IS LOCKED OUT PROBLEM COULD INDICATE FALSE POSITIVE PROOF OF AIR FLOW BLOCKED VENT...

Page 49: ...low the gas supplier s instruction If you can not reach your gas supplier call the fire department Should overheating occur or the gas supply fail to shut off do not turn off or disconnect the electri...

Page 50: ...50 TROUBLESHOOTING CHART 2 Troubleshooting...

Page 51: ...CONDENSATE MAY PUDDLE AND BLOCK THE VENT YES CHECK AIR PRESSURE SWITCH PER INSTRUCTIONS ON FOLLOWING PAGES ARE SAMPLING LINES CLEAR AND CONNECTED PROPERLY NO CLEAN OUT SAMPLING LINES OR REPLACE DEFEC...

Page 52: ...ACROSS TERMINALS MV ON THE GAS CONTROL WHILE VALVE FLAME INDICATOR LIGHT IS ON NO NO CHECK FOR 24 VAC ACROSS TERMINALS CN6 2 AND CN6 5 ON IBC WHILE THE VALVE FLAME LED IS LIT NO REPLACE IBC YES REPAI...

Page 53: ...53 TROUBLESHOOTING CHART 5 Troubleshooting...

Page 54: ...SPECIFIC TOOLS NO YES REPLACE BURNER REPLACE IBC BOILER SHUTS OFF BEFORE END OF CALL FOR HEAT ARE HI LIMIT AQUASTAT CONTACTS CLOSED NO BOILER OFF ON HIGH LIMIT IS ACTUAL BOILER WATER TEMP GREATER THA...

Page 55: ...heat Boiler Status Differential Pressure w c Pressure Switch Connects Not Running 0 Normally Open Setpoint 1 00 for Model 100 1 35 for Model 75 1 55 for Model 50 Running Without Blockage Greater Than...

Page 56: ...85 Middle Rd Dunkirk NY 14048...

Reviews: