2-22
EPQ DataNode Series User’s Guide
2
Preparation for Use
LINE
LOAD
A B C
Fuses
Switchgear
Chassis Ground
CT Shorting Switch
or Test Block
To Switchgear Chassis Ground*
DataNode 5510/5530: Connecting Power to the Input Pods
(New model Voltage and Current Pods shown)
Connection Type: 3 WIRE DELTA, 3 ELEMENT DIRECT
Setup Mode: Delta
Connections must be performed in
compliance with all safety requirements
applicable to your installation.
*NOTE: Connections of CT leg to
ground is recommended, but not
required for proper operation.
Refer to Fuse Warnings on page 2-12