Process enclosure, extract offtake(s), hose/ducting and extract/filtration unit.
Inspection and Maintenance Record
1. Daily inspection
Inspection of the process to ensure extract devices/nozzles/enclosures/hoses are in place and correctly
positioned. Examination of the extractor to ensure it is running. This to be carried out by the operator. Daily
inspection not recorded.
2. Weekly Inspection
Weekly inspection by supervisor of physical condition of extract devices/nozzles/enclosures/hoses and
extraction unit for damage, change (parts added or removed) and correct operation etc. Check also that daily
inspections have been completed. Tick boxes to confirm system ok / change. Add details of any changes.
Report changes to Engineering Manager. Record any remedial actions taken.
Week
number
Date
System
ok
System
Change
Details of change / repairs etc
Initial
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26