7
Tower Installation with battery pack
Step 1
Step 2
2-4. Setup the UPS
Before installing the UPS, please read below to select proper location to install UPS.
1.
UPS should be placed on the flat and clean surface. Place it in an area away from vibration,
dust, humidity, high temperature, flammable liquids, gases, corrosive and conductive
contaminants. Install the UPS indoors in a clean environment, where it is away from
window and door. Maintain minimum clearance of 100mm in the bottom of the UPS to
avoid dust and high temperature.
2.
It’s required to maintain maximum altitude of 3000m to keep UPS normal operation at full
load UPS.
3.
Place UPS:
It’s equipped with fan for cooling. Therefore, place the UPS in a well-ventilated area. It’s
required to maintain minimum clearance of 100mm in the front of the UPS and 300mm in the
back and two sides of the UPS for heat dissipation and easy-maintenance.
Step 1: External battery connection
For safety consideration, the RT UPS is shipped out from factory without connecting battery
wires. Before connecting to external batteries, it’s required to have the internal battery wire
disconnected. Follow the below steps to make external battery connection.
1. Turn off UPS and remove power plug from the mains.
2. Remove front panel and disconnect internal battery wire. (only available for RT models with
internal battery wire connected)