6. Connect the load positive ( + ) cable and load negative ( - ) cable to the
opposing ends of the parallel batteries.
LOAD (+)
LOAD (-)
Figure 6. Load Connections.
7. Connect the charger positive ( + ) cable and charger negative ( - ) cable
to the opposing ends of the parallel batteries.
LOAD (+)
LOAD (-)
CHARGER (-)
CHARGER (+)
Figure 7. Charger Connections.
8. Torque all battery terminals to the recommended terminal torque of 13
Nm (9.6 ft-lb) to secure cable lugs.
NOTICE
Failure to properly torque battery terminal nuts may increase resistance and lower voltage
which may lead to burnout of the terminals and void the warranty.
NOTE
Wherever replacing an old battery in a string, use a battery of the same age, model,
capacity, and voltage.
NOTE
Before installing the battery in parallel, ensure that each battery is charged to 100% SOC.