13
4
4
Assembling the upper assembly
1. Lay the upper assembly on a non-abrasive surface, such as the carton or a table. Remove the 8 pre-
installed screws from the back panel of the upper post. These are identical to hardware
A
.
(Figure 7)
2. Insert the regulator with hose through the upper post.
(Figure 8)
3. Re-install the back panel of the upper post.
(Figure 9)
4. Insert the middle post in the upper post and secure it using 6 x hardware
A
.
(Figure 9)
5. Secure the heater to the upper post using hardware
D
,
E
,
F
, and
G
as shown.
(Figure 10)
Installation
Pre-installed
screws (×8)
Figure 7
Regulator
with Hose
Figure 8
×6
Previously removed
screws (×8)
A
Figure 9
G
D
E
F
Figure 10
G
D
E
F
A
×6