SERVICE BULLETIN 010
LC / LV FACTORY START-UP SUPERVISION
A Factory Start-Up
requires a Desert Aire Service Department Technician to visit the jobsite and provide supervisory experience to
installing contractors as they perform the required procedures as outlined in our warranty activation Start-Up Report. The company
technician will also present an educational review of the dehumidifier’s operating and maintenance requirements.
A CST Start-Up
is performed by a local Certified Service Technician who has been trained by Desert Aire. The CST performs all
duties of commissioning and also trains responsible parties on the proper maintenance and operation of the unit.
“Factory Start-Up is not an installation bid & therefore the system must be ready to run before scheduling.”
The Desert Aire Service Dept. will advise contractors of their responsibilities and coordinate all site visits. This start-up procedure
may be performed by Desert Aire OR an authorized Certified Service Technician. This document requires a signature and must be
returned to Desert Aire before the Factory- or CST-supervised start-up can be scheduled. Desert Aire will confirm the start-up dates
upon receipt of the pre-start-up checklist.
If a return trip must be scheduled due to insufficient jobsite preparation, a second
P.O. # must be issued to Desert Aire for re-scheduling.
The following list of items will apply to all start-ups and is the responsibility of the installing contractor. If you are unable
to supply any of the following equipment, you must contact Desert Aire before signing this document. You can reach
Desert Aire at (262) 946-7400.
Items needed for Start-Up:
q
Equipped service vehicle and service technician – Technician will be trained.
q
Refrigerant manifold gauges – 2 sets
q
Air balancing equipment (Magnehelic® or manometer differential pressure gauge)
q
Volt/Amp/OHM meters in working order.
q
Digital thermometer w/clamp on sensors OR laser type temperature probe
q
50# of refrigerant & weigh in scale
q
Hand pump for adding oil to compressor (Copeland Scroll) 9-ton compressor & larger (R-22 requires 150 viscosity 3 GS
mineral oil. R-410A requires Copeland’s POE Genetron® AZ20/Suva® 9100 for new start-ups.)
Items to be completed before Start-Up:
q
Dehumidifier leak checked (with halogen leak detector) and inspected for internal concealed damage –
remove access panels and inspect the interior of the unit for transit damage. Contact Desert Aire
immediately if damage is noted.
(262) 946-7400
q
Dehumidifier leveled and properly supported per the installation manuals recommendations.
q
Outdoor air duct filters and damper installed (if applicable). – See installation manual.
q
Condensate P Trap installed with heat trace for winter operation.
q
Remote condenser plumbed and inspected for freight damage (If applicable).
q
Remote condenser circuit leak checked, evacuated and charged (if applicable). – See installation manual
for refrigerant weights and condenser locations.
q
All electrical connections terminated and verified for proper voltage at the unit.
q
All field controls and sensors installed and circuits verified that they are wired correctly. If there are any
questions, contact Desert Aire Service at
(262) 946-7400.
q
Pool filled and water and air temperatures at a minimum of 80° (if applicable).
q
Pool water heating circuit connected to dehumidifier with flow meter and balancing valves installed in
circuit (if applicable).
q
Verify the installation of the booster pool water heating pump and purge air from the water lines
(if applicable).
q
Verify that voltage matches nameplate design for the condenser and the dehumidifier.
A MINIMUM TWO WEEK LEAD TIME IS NEEDED TO SCHEDULE START-UP