background image

www.desatech.com

116010-01E

8

VenTing insTallaTion

Continued

FIRESTOP SPACERS (1100EFS-10DM)

Firestop spacers are required at each point 
where  chimney  penetrates  a  floor  space. 
Their  purpose  is  to  establish  and  maintain 
required  clearance  between  chimney  and 
combustible  materials.  When  pipe  passes 
through a framed opening into a living space 
above, firestop must be placed onto ceiling 
from below as shown in Figure 10.
They also provide complete separation from 
one floor space to another or attic space as 
required  by  most  codes.  When  double  wall 
pipe passes through a framed opening into 
an attic space, firestop must be placed into 
attic floor as shown in Figure 11.

Figure 10 - Firestop Spacer with Living 

Space Above Ceiling

Figure 11 - Firestop Spacer with Attic 

Space Above Ceiling

Existing 
Ceiling 

Frame

Firestop 

Spacer

Screws or 
Staples 
(Min. of 8)

Firestop 

Spacer

Screws or Staples 
(Min. of 8)

PENETRATING THE ROOF

To maintain a 1" clearance to the pipe on a 
roof with a pitch, a rectangular opening must 
be cut.
1.  Determine the center point through which 

pipe will penetrate the roof.

2.  Determine center point of the roof. Pitch 

is the distance the roof drops over a given 
span, usually 12". A 6/12 pitch means the 
roof drops 6" for each 12" one measure 
horizontally down from roof rafters.

3.  Use roof opening chart (Figure 12, page 

9) to determine correct opening length and 
flashing required.

4.  Remove shingles around opening mea

-

sured. Cut out this section.

Existing 
Ceiling 

Frame

Figure 9 - Typical Offset Terminations

Return 
Elbow

Offset 
Elbow

Return 
Elbow

Offset 
Elbow

6' Max.

6' Max.

6' Max.

6' Max.

6' Max.

6' Max.

Return 
Elbow

Offset 
Elbow

Offset 
Elbow

Return 
Elbow

A

B

C

Offset 
Elbow

Ceiling 
Support Pipe
12S-12DM

Return 
Elbow

Summary of Contents for (V)G36

Page 1: ...ies with UL127 CAN ULS S610 M87 standard as a FACTORY BUILT APPLIANCE FOR CANADA The authority having jurisdiction such as the municipal building department fire department etc should be contacted bef...

Page 2: ...omponent part not manu factured or approved by DESA Heat ing LLC in combination with a DESA Heating LLC fireplace system Proper installation is the most important step in ensuring safe and continuous...

Page 3: ...ACH SIDE COMBUSTIBLE WALL BOARD NO COMBUSTIBLE MATERIAL ON FACE MINIMUM 12 TO PERPENDICULAR SIDEWALL HEARTH EXTENSION 74 X 20 1 CHIMNEY AIRSPACE CLEARANCE TO COMBUSTIBLE MATERIAL TERMINATION SQUARE CH...

Page 4: ...et This measurement includes fireplace chimney sections and height of termination assembly at level of the flue gas outlet see Figure 15 page 9 28 25 58 125 67 125 45 25 Figure 1 Framing Dimensions 86...

Page 5: ...e 3 WARNING Hearthextension is to be installed only as shown in Figure 3 Fireplace Installation Continued Figure 3 Hearth Extension Seal Gap Fireplace Front Ember Protector Fireplace Front Raised Hear...

Page 6: ...equired for Wall Installation Air Inlet Eyebrow Vented Crawl Space Check Local Codes Before Installing in a Vented Crawl Space Optional Outside air Kit Model ak4 ak4f Installation of an outside air ki...

Page 7: ...th of double wall pipe see offset chart and Figure 7 2 Chimney weight above offset rests on return elbow Straps must be securely nailed to rafters or joists see Figure 8 details a and b 3 Maximum leng...

Page 8: ...th Attic Space Above Ceiling Existing Ceiling Frame Firestop Spacer Screws or Staples Min of 8 Firestop Spacer Screws or Staples Min of 8 Penetrating the roof To maintain a 1 clearance to the pipe on...

Page 9: ...area and flashing base Secure in position by nailing through shingles see Figure 13 DO NOT NAIL THROUGH FLASHING CONE Figure 14 Storm Collar Chimney Pipe Waterproof Caulk Storm Collar Flashing Install...

Page 10: ...shed Side Refractory Knockout Plug Outside of Fireplace Gas Line Conduit Insulation Gas Conduit Cover 1 2 Dowel Remove Knockout Optional Gas Line Installation CAUTION Do not seal open ingsontherooftop...

Page 11: ...E FOR LEAK TESTING AND DO NOT OPER ATEANYAPPLIANCE IFALEAK IS DETECTED LEAK TESTING SHOULD BE DONE BYAQUALI FIED SERVICE PERSON Seal Opening with Refractory Cement Outside of Fireplace Gas Line Condui...

Page 12: ...y open doors enough so that you can access spring clips with a phillips screwdriver Tighten screws See Figure 23 Figure 22 Installing Bi Fold Doors Spring Clip Insert Pin into Spring Clip Pivot Hole I...

Page 13: ...rsfullyopenedordoorsfully closed Doors ifleftpartlyopen may draw gas and flame out of the fireplace opening creating risks of both fire and smoke Cleaning Glass Clean glass with any commercial glass c...

Page 14: ...s 116084 02 G36 Models Right Brick Refractory 116082 01 VG36 Models 116082 02 G36 Models Left Brick Refractory 116081 01 VG36 Models 116081 02 G36 Models Rear Brick Refractory 116083 01 VG36 Models 11...

Page 15: ...eady You can also visit DESA Heating LLC s web site at www desatech com Replacement Parts Continued Accessories Bi Fold Glass Door BDG36 36 Black Finish BDG36B 36 Brushed Brass Finish BDG36P 36 Platin...

Page 16: ...2 Pitch SQUARE CHASE TOP TERMINATION STL 12D Round ToP TErminations RLT 12D and RLT 12HT DESA Heating LLC 2701 Industrial Drive Bowling Green KY 42101 www desatech com NOT A UPC 116010 01 Rev E 06 08...

Reviews: