INSTALLATION

Built-in installation of this fireplace involves in-

stalling fireplace into a framed-in enclosure. This 

makes the front of fireplace flush with wall. Follow 

the instructions below to install the fireplace in this 

manner. If installing a built-in mantel above the 

fireplace, you must follow the clearances shown 

in Figure 8, page 11. 

Note:

 If desired, purchase a four-sided trim kit for 

built-in installations. See 

Accessories

, page 35. 

 

 

Actual 

Framing

 

Height 

26" 

26 

7

/

8

"

 

Front Width 

26 

3

/

4

26 

7

/

8

"

 

Depth 

1

/

2

10 

1

/

2

"

 

Bottom 

3/4" 

3/4"

INSTALLATION

Continued

An  optional  blower  kit  is  available  from  your 

dealer. See 

Accessories

, page 35. If planning to use 

blower, locate fireplace near an electrical outlet.

Minimum Clearances For Side Combustible 
Material, Side Wall, and Ceiling 

A.  Clearances  from  the  side  of  the  fireplace 

cabinet to any combustible material and wall 

should follow diagram in Figure 4.

 

Example: 

The face of a mantel, bookshelf, 

etc.  is  made  of  combustible  material  and 

protrudes 3 

1

/

2

" from the wall. This combus-

tible material must be 4" from the side of the 

fireplace opening (see Figure 4).

B.  Clearances from the top of the fireplace open-

ing to the ceiling should not be less than 42 

inches.

Figure 4 - Minimum Clearance for 

Combustible to Wall 

*Minimum 16 inches from Side Wall 

*

Example

1.  Frame in rough opening. Use dimensions shown 

in Figure 5 for the rough opening.

 

If installing in a corner, use dimensions shown 

in Figure 6 for the rough opening. The height 

is 26 

1

/

8

" which is the same as the wall opening 

above.

2.  An optional blower accessory is available (see 

Accessories

, page 35). There are two options 

for connecting blower to electrical source.

 

Option one:

 Have a licensed electrician install 

a  properly  grounded,  three-prong  120-volt 

electrical outlet at fireplace location. Locate 

outlet inside the framed enclosure. Blower 

power cord will plug into this outlet.

 

Option two:

 Have a licensed electrician con-

nect blower to electrical source at junction box 

inside fireplace.

 

If using option one, have electrical outlet in-

stalled at this time. If using option two, do not 

connect blower to electrical source at junction 

box until step 6.

3.  Install gas piping to fireplace location. This 

installation includes an approved flexible gas 

line (if allowed by local codes) after the equip-

ment shutoff valve. The flexible gas line must 

be the last item installed on the gas piping.

4.  Carefully set fireplace in front of rough opening 

with back of fireplace inside wall opening.

5.  Attach flexible gas line to fireplace gas regula-

tor. See 

Connecting Fireplace to Gas Supply

page 16.

36

5

/

8

"

25

7

/

8

"

51

3

/

4

"  

26

7

/

8

"

Figure 6 - Rough Opening for Installing 

in Corner 

26

7

/

8

"

26

7

/

8

"

3/4" Off
The Floor
Minimum

10 

1

/

2

"

Figure 5 - Rough Opening for Installing 

in Wall 

Summary of Contents for Comfort Glow CF26NRA

Page 1: ...light any appliance Do not touch any electrical switch do not use any phone in your building Immediatelycallyourgassupplierfromaneighbor s phone Follow the gas supplier s instructions If you cannot re...

Page 2: ...in an aftermarket per manently located manufactured mobile home where not prohibited by local codes This appliance is only for use with the type of gas indi cated on the rating plate This appliance i...

Page 3: ...ll warn ings Keep this manual for reference It is your guide to safe and proper operation of this heater WARNING Any change to this heater or its controls can be dangerous WARNING Do not use a blower...

Page 4: ...eds fresh air ventilation to run properly This replace has an Oxygen Deple tion Sensing ODS safety shutoff system The ODS shuts down the replace if not enough fresh air is available See Air for Combus...

Page 5: ...air for this and other fuel burning appliances in your home Today s homes are built more energy ef cient than ever New materials increased insulation and new construction methods help reduce heat loss...

Page 6: ...rnished with doors are considered a part of the uncon ned space Adjoining rooms are communicating only if there are doorless DETERMINING FRESH AIR FLOW FOR FIREPLACE LOCATION Determining if You Have a...

Page 7: ...rovide two perma nent openings one within 12 of the ceiling and one within 12 of the oor on the wall connecting the two spaces see options 1 and 2 Figure 2 You can also remove door into adjoining room...

Page 8: ...ARNING Maintainthemini mumclearancesshowninFigure 4 page 9 If you can provide greater clearances from oor ceiling and joining wall You can recess rebox into the wall You can also position replace in t...

Page 9: ...ble to Wall Minimum 16 inches from Side Wall Example 1 Frameinroughopening Usedimensionsshown in Figure 5 for the rough opening If installing in a corner use dimensions shown in Figure 6 for the rough...

Page 10: ...rlap the rebox front facing IMPORTANT Noncombustible materials such as brick tile etc may overlap the front facing but should never cover any necessary openings like louvered slots WARNING Do not allo...

Page 11: ...ting plate shim in slot on mitered edge of side trim see Figure 9 6 While rmly holding edges of trim together tighten both set screws on the adjusting plate with slotted screwdriver 7 Repeat steps 1 t...

Page 12: ...connection when servicingcontrols Wiringerrors cancauseimproperanddanger ous operation CAUTION Verify proper op eration after servicing Note If you are using a mantel with your heater use the followin...

Page 13: ...5 9 Reconnect red wire to theAUTO switch posi tion Reconnect blue wire to the ON switch position Reconnect green and white wires to the power cord 10 Install the switch plate on the blower control shi...

Page 14: ...nector not included Outlet Receptacle Strain Relief Blue Red 1 Install a snap bushing found in hardware kit into one of the holes found on rear of blower control shield The other hole is for a strain...

Page 15: ...supply an external regulator The external regulator will reduce incoming gas pressure You must reduce incoming gas pressure to between 11 and 14 inches of water If you do not reduce incoming gas pres...

Page 16: ...valve from your dealer See Accessories page 35 Minimum inlet pressure for purpose of input adjustment 3 Minimum Gas Control Propane LP From External Regulator 11 W C to 14 W C Pressure Natural From Ga...

Page 17: ...trol valve and equipment shutoff valve from gas supply piping system Pressures in excess of 1 2 psig will damage heater regulator 2 Cap off open end of gas pipe where equipment shutoff valve was conne...

Page 18: ...diagrams or failure to use only parts speci cally approved with this heater may result in property damage or personal injury CAUTION After installa tion and periodically thereafter check to ensure tha...

Page 19: ...ne batteries Installing 9 Volt Battery in Receiver 1 Locate back of receiver under front burner of heater 2 Locate the battery clip mounted on the back of the receiver 3 Slide a 9 volt battery through...

Page 20: ...re equipment shutoff valve is fully open 3 Set switch in OFF position WARNING Burner will come on automatically within one minutewhentheselectorswitch is in the ON position after the pilot is lit 4 Pr...

Page 21: ...hrough 6 under Lighting Instructions page 20 2 Depress control knob and light pilot with match 3 Keep control knob pressed in for30 seconds after lighting pilot After 30 seconds release control knob N...

Page 22: ...for any reason cannot transmit to the receiver the receiver will shut off the replace after 8 minutes Key Pad Lock Feature This feature allows the user to lock unlock the keypad on the hand held remo...

Page 23: ...5 Figure 41 Correct Flame Pattern with Control Knob Set to High Flame Figure 42 Incorrect Flame Pattern with Control Knob Set to High Flame Approx 3 6 Above Top of Logs More Than 8 Above Top of Logs B...

Page 24: ...utes 2 Inspect burner pilot and primary air inlet holes on injector holder for dust and dirt see Figure 43 3 Blow air through the ports slots and holes in the burner 4 Check the injector holder locate...

Page 25: ...nd base panel 4 Replace ignitor cable 5 Replace piezo ignitor 6 Replace pilot assembly 7 Replace pilot assembly 1 Turn on gas supply or open equipment shutoff valve 2 Turn control knob to PILOT positi...

Page 26: ...ully open equipment shutoff valve 4 A Contact local natural or propane LP gas company B Clean ODS pilot see Cleaning and Maintenance page 23 or replace ODS pilot assembly 5 Hand tighten until snug the...

Page 27: ...e burners until air is removed from line Have gas line checked by local natural or propane LP gas company 3 Observe minimum installation clearances see page 9 4 Clean burners see Cleaning and Maintena...

Page 28: ...ro pane LP gas company 3 CleanODS pilot seeCleaning and Maintenance page 23 1 Locate and correct all leaks see Checking Gas Connec tions page 17 2 Replace control valve 1 Take apart gas tubing and rem...

Page 29: ...Inlet Gas Pressure in of water Maximum 14 10 5 Minimum 11 5 Dimensions H x W x D Fireplace 25 7 8 x 27 x 13 3 4 25 7 8 x 27 x 13 3 4 Carton 28 x 26 13 16 x 16 1 2 28 x 26 13 16 x 16 1 2 Weight pounds...

Page 30: ...tech com 113897 01A 30 ILLUSTRATED PARTS BREAKDOWN MODELS CF26PRA AND CF26NRA 10 24 25 O F F P I L O T O N H I L O O F F P I L O T O N H I L O 16 15 19 8 19 20 21 17 18 14 13 23 12 22 13 4 7 6 9 5 11...

Page 31: ...80 01 102980 01 Burner 1 10 099387 13 099387 15 Pilot Tube 1 11 103781 02 103781 01 Gas Control Valve 1 12 103345 02 103345 02 Lower Bracket 1 13 M11084 38 M11084 38 Screw 8 x 38 7 14 104384 04 104384...

Page 32: ...www desatech com 113897 01A 32 ILLUSTRATED PARTS BREAKDOWN MODELS CF26PRA AND CF26NRA 5 8 15 17 13 14 11 2 11 1 19 4 12 16 10 6 5 9 1 2 18 7 20 2 20 3 20 1 18 18 16 21 3 18 16 3 21...

Page 33: ...er 1 8 105255 01 Bayfront Base 1 9 105421 01 Heat De ector 1 10 105409 01 Fan Control Shield 1 11 1 105401 01 Screen Rod 1 11 2 105440 01 Screen Assembly 1 12 101386 02 Hinge 2 13 099194 11 Rivets 8 1...

Page 34: ...uestions about installation operation or troubleshooting If so contact DESA Heating Products Technical Service Department at 1 866 672 6040 When calling please have your model and serial numbers of yo...

Page 35: ...g heater to be turned on and off by using a hand held remote control BRASS ACCENT TRIM GA7092 Not Shown Optional two piece trim kit for the Bayfront Fire place Easily screws to replace front Provides...

Page 36: ...such other costs related to repairing a defective replace will be the responsibility of the owner TO THE FULL EXTENT ALLOWED BY THE LAW OF THE JURISDICTION THAT GOVERNS THE SALE OF THE PRODUCT THIS EX...

Reviews: