Quick installation guide for RPI M6A M8A M10A inverters
Commissioning - Basic Settings
11
DISCONN AC/DC
OFF
ON
To commission the inverter, it needs to be powered either by AC (the grid) or DC (the solar
modules)
After powering up the inverter for the fi rst time, the
Select language
dialog is shown
F r a n ç a i s
D e u t s c h
E n g l i s h
S e l e c t l a n g u a g e
1.
Use the buttons
and
to select language
English
To confi rm your selection, press the button
ENT
C H I N A 2 0 1 3
C H I N A M V
C Z E C H
E N G L A N D
F R A - I s 5 0 H Z
2.
Use the buttons
and
to select your country or grid type
To confi rm your selection, press the button
ENT
Y E S / N O
E N G L A N D
s e t c o u n t r y :
A r e y o u s u r e t o
3.
If the selected country is correct, use the buttons
and
to select the entry
YES
To confi rm your selection, press the button
ENT
If you want to change your selection, press the button
ESC
→
The inverter starts a self-test which takes approximately 2 minutes A countdown
shows the remaining time on the display
;
The basic setup is fi nished. The standard menu is shown.
E - T o d a y : 0 k W h
P o w e r : 0 W
S t a t u s : O n G r i d
1 0 . S e p 2 0 1 4 1 5 : 3 2
►
Check the next chapter of this quick installation guide whether you need to adjust addtional settings