5.2

检查内容

 

5.2 Check Content 

5.2.1 检查仪表外观是否有缺陷,损坏等异常情况,石英玻璃管和玻璃条是否有裂纹,阀门与主体
之间的活接头是否松动。 
5.2.1 Check the appearance of the instrument for defects, damage and other abnormal conditions, 
whether the quartz glass tube and the glass strip are cracked, and whether the joint between the 
valve and the main body is loose. 
 

6

安装

 

6 Installation 

6.1

安装工具

 

6.1 Installation Tool 

6.1.1 适用于过程连接件的扳手、法兰垫片和法兰螺栓 
6.1.1 Wrenches, flange gaskets and flange bolts for process connections 
6.1.2 水平仪 
6.1.2 Level 

6.2

安装技术要求

 

6.2 Installation Technical Requirements 

6.2.1 在安装液位计之前需要测量容器上的法兰中心距是否与液位计的中心距一致,如不一致,需
要调整容器或液位计的法兰中心距,强行安装容易损坏液位计。 
6.2.1 Before installing the level gauge, it is necessary to measure whether the center distance of the 
flange on the container is consistent with the center distance of the level gauge. If it is inconsistent, 
the flange center distance of the container or the level gauge needs to be adjusted, and the level 
gauge is easily damaged by forced installation. 
6.2.2 安装液位计时,液位计法兰轴线必须垂直于水平面-图 4。 
6.2.2 When installing the level gauge, the level of the level gauge flange must be perpendicular to 
the horizontal plane - Figure 4. 

调试

 

7 Debugging 

Summary of Contents for ULG

Page 1: ...1 16 WWW DDTOP COM ULG ULG S BI COLOR GLASS TUBE LEBEL GAUGE ULG Operation Manual ULG DT JS 1010 2018 A...

Page 2: ...er may be destroyed Trademark Copyright and Restriction Instructions DDTOP Dandong Top Electronics Instrument Group Co Ltd Dandong Top Pump Co Ltd DDTOP are registered trademarks of the company The pe...

Page 3: ...dong Top Electronics Instrument Group Co Ltd does not provide any express or implied warranty Quality ISO9001 Dandong Top Electronics Instrument Group Co Ltd has passed the ISO9001 quality system cert...

Page 4: ...onal Schematic 7 5 9 5 Unpacking and Inspection 9 5 1 9 5 1 Unpacking Inspection Notice 9 5 2 11 5 2 Check Content 11 6 11 6 Installation 11 6 1 11 6 1 Installation Tool 11 6 2 11 6 2 Installation Tec...

Page 5: ...able local national international standards codes and procedures Be sure to install the equipment in Intrinsically safe or non flammable site operating procedures 1 2 1 2 Process leaks can cause serio...

Page 6: ...alve 2 2 Compression Body 3 3 Socket Head Cap Screws 4 4 Graphite Filler 5 5 Quartz Glass Tube 6 6 Ruler 2 2 2 2 Operating Principle According to the principle of the connector the level in the contai...

Page 7: ...dity 20 3 3 Technical Characteristics 3 1 3 1 Main Performance 3 1 1 JB T9243 3 1 1 Product Performance Standards JB T9243 glass tube level gauge 3 2 3 2 Main Parameters 3 2 1 0 3MPa 3 2 1 Needle valv...

Page 8: ...Schematic S1 Glass Tube Level Gauge 2 2 S2 Figure 2 2 Dimensional Schematic S2 Glass Tube Level Gauge 2 3 S4 Figure 2 3 Dimensional Schematic S4 Glass Tube Level Gauge 2 4 S5 Figure 2 4 Dimensional S...

Page 9: ...9 16 WWW DDTOP COM 2 3 S4 Figure 2 3 S4 Glass Tube Level Gauge 2 4 S5 Figure 2 4 S5 Glass Tube Level Gauge 5 5 Unpacking and Inspection 5 1 5 1 Unpacking Inspection Notice 5 1 1 3...

Page 10: ...1 Check whether the product nameplate Figure 3 is consistent with the supply list information 3 Figure Product Nameplate 5 1 2 5 1 2 According to the packing list check the quantity of each part and...

Page 11: ...onnections 6 1 2 6 1 2 Level 6 2 6 2 Installation Technical Requirements 6 2 1 6 2 1 Before installing the level gauge it is necessary to measure whether the center distance of the flange on the conta...

Page 12: ...12 16 WWW DDTOP COM 4 Figure 4 Debugging 7 1 1 4...

Page 13: ...the medium to flow into the level gauge Valve 4 7 5 2 4 7 5 Fully open the upper and lower valves of the gauge Valve 2 Valve 4 8 8 Failure Analysis and Elimination Fault Phenomenon Reason Method of E...

Page 14: ...es Valve 1 Valve 2 Valve 3 Valve 4 remove the drain plug and drain the residual medium See Figure 5 9 2 2 6 9 2 2 Remove the hexagon socket head cap screws diagonally See Figure 6 9 2 3 9 2 3 After re...

Page 15: ...ll and the end face of the glass tube is basically the same as that of the shell 9 4 2 9 4 2 Insert graphite packing ring into both ends of quartz glass tube 9 4 3 9 4 3 Install the compression body a...

Page 16: ...16 16 WWW DDTOP COM...