background image

5

 

Davey supply a range of control boxes incorporating various switching devices and the use of these products 
is recommended.  Alternative systems may be connected directly into the supply line to 240 volt motor control 
boxes, provided the switching device used has an adequate current rating.  If the current rating of the switch is 
not adequate, a contactor must be wired into the supply and the switching device used to control the contactor’s 
coil.  In any case, where a single phase motor has a control (starter) box, no additional switching devices should be 
wired between the motor and box.

 

In the case of three phase motors, all switching devices should be wired to the starter’s control coil, and on no 
account should they be used to directly break the supply circuit to the pump.

6. 

Electrical Connection

 

All wiring should conform to the requirements of local and national electrical codes.  If in doubt, contact your 
electricity supply authority.  Cables should be insulated and sheath type, conforming to AS3100 and rated for 
continuous immersion in water.

 

For full motor connection details consult the relevant motor installation & operating instructions.

WARNINGS:
A. 

BEFORE installing or servicing your pump check to ensure that electrical power is turned off and 
disconnected.

B. 

Single phase motors with in-built thermal overloads may restart automatically and unexpectedly.  Ensure 
that warning A. above is observed at all times.

 

All electrical connections should be checked before the pump is installed in the bore.  If possible, it is a good 
practice to run the pump briefly in a container of water (water level must be well over the suction inlet screen) to 
check on operation before installation in the bore.  The drop cable should be secured to the drop pipe at three (3) 
metre intervals using waterproof plastic tape.

7. 

Direction of rotation - Three phase motors only

 

Any three phase motor connected to a supply line for the first time may rotate in either direction.  It is, therefore 
necessary to find out it the motor is rotating in the correct direction.  If the rotation is to be checked on the surface, 
proceed as follows:

 

-  Pour clean water into the discharge by holding the non-return valve open so that the shaft bearings and 

impellers become wet.

 

-  Turn the power on and off for a very short time and check the shaft rotation.

 

-  The correct rotation is anti-clockwise by looking down from the discharge.

 

-  To correct a reversed rotation, change any two leads (except earth) from the three phase supply at the motor 

starter.

8. 

Three Phase Connection

 

Three phase models must be wired with a contactor with approved ‘quicktrip’ overloads set correctly.

 

Davey recommend the use of overloads which also have the ability to detect “single phasing” or “dropped phase” 
conditions in the power supply.

WARNING: The dry rotation should not exceed a period of one to two seconds, otherwise seizing may 
occur due to inadequate lubrication.

Before finalising wiring connections, check that motor rotates in direction of arrow (clockwise when 
shaft is viewed from wiring connection end).  To alter rotation, change any two power leads at motor 
terminals.

POWER CONNECTIONS AND WIRING MUST BE CARRIED OUT BY AN AUTHORISED ELECTRICIAN.

ALL THREE PHASE MOTORS MUST BE CONNECTED WITH APPROVED QUICK TRIP OVERLOADS.

Summary of Contents for J Series

Page 1: ...ING The pump and associated pipework operate under pressure Under no circumstances should the pump or associated pipework be disassembled unless the internal pressure of the unit has been relieved Fai...

Page 2: ...the pump a cascading bore or where the pump is installed in a large diameter bore or in a river or other open water sources a shroud may be required over the pump to ensure that all water being pumped...

Page 3: ...3 metres above the bottom of the bore and one 1 metre below the maximum draw down level WARNING If during the initial operation the pump lowers the bore water level down to below the suction inlet it...

Page 4: ...a drilled check valve to the pressure tank may assist in the prevention of pump cycling problems For further information on these contact your Davey Dealer NOTE Any automatic switching of the pump gi...

Page 5: ...od practice to run the pump briefly in a container of water water level must be well over the suction inlet screen to check on operation before installation in the bore The drop cable should be secure...

Page 6: ...restarting the pump Davey submersibles are not guaranteed against failure due to pumping sand Pumping of sand even small quantities of very fine sand will shorten the effective life of any pump The pu...

Page 7: ...r 2 No water delivered Water level in bore too low Check valve installed backwards or stuck closed Inlet screen on pump clogged Hole in delivery piping below bore top Motor failure Broken pump shaft o...

Page 8: ...Phone Driller s Estimate Yield gph lph m3 ph Other Rock Types drilled through Was a Bore Yield Test undertaken YES NO What type of Bore Test 1 Bailed Blown by Driller or 2 Pumped with Test Pump to max...

Page 9: ...NOTES 9...

Page 10: ...NOTES 10...

Page 11: ...does not cover freight or any other costs incurred in making a claim Please retain your receipt as proof of purchase you MUST provide evidence of the date of original purchase when claiming under the...

Page 12: ...UD Group ABN 18 066 327 517 NEW ZEALAND Davey Support Centre 7 Rockridge Avenue Penrose Auckland 1061 Ph 0800 654 333 Fax 09 527 7654 Website daveynz co nz Davey is a registered trademark of Davey Wat...

Reviews: