User Guide
|
Plate Type Heat Exchangers, Single plate & Semi-welded - Installation, Commissioning and Maintenance
© Danfoss | DCS (ms) | 2019.07
BC172686461130en-000201 | 9
Installation
(Continued)
Transport and lifting
WARNING:
To prevent personal injury always use
appropriate hoisting equipment. If you
are to lift the heat exchanger itself,
straps should be used. The straps
should be placed as shown in fig. 8.
Usually the heat exchanger will be supplied
horizontally on a pallet.
The back side of the head will then be secured
to the pallet. This allows the unit to be
transported by means of a forklift truck.
Raising of the unit: see fig. 8.
• Remove all tightening elements from the pallet
• Place straps around opposite bolts on each side
of the column (1)
• Lift the unit vertically from the pallet (2)
• Remove the pallet securely (3)
• Slowly lower the heat exchanger to the floor (4)
• Remove the straps at the unit bottom side (5)
• Lift one-sided in an appropriate lifting angle (6)
and follow the raising of the unit carefully.
Avoid any bumps or shocks
• Once the heat exchanger is in upright position
place the straps in the dedicated lifting eyes (7)
and lift the unit to its final position (8)
• Remove the straps and mount the heat
exchanger securely to the floor
Fig. 8. Lifting instructions
Never lift the heat exchanger using any
other method than described above.
Never use the connections, studs or any
intermediate plates (if fitted) for lifting
(fig. 9).
Fig. 9. Lifting points not allowed