Study the illustration of the pole mounting method in
Drawing A-102469
, and then
use the following procedure for each display:
1.
Measure the beam spacing and drill a 9/16" diameter hole for each 1/2"
threaded rod through one flange of the clamping channels.
2.
Insert the threaded rods through the drilled opening and secure using 1/2"
nuts and lock washers.
3.
Position the display at the front of the beams with the threaded rods
extending from the rear of the channels, straddling the poles.
4.
Raise the display to the desired height.
5.
Slide clamping angles over the ends of the threaded rods and loosely install
1/2" washers and nuts.
6.
Make final adjustments in positioning the display. Make sure the threaded
rods are perpendicular to the display.
7.
Tighten all the 1/2" hardware.