13 Unit installation

Installation and operation manual

16

RWEYQ8~14T9Y1B

VRV IV water-cooled system air conditioner

4P452190-1D – 2020.10

g

Boiler

13

Unit installation

13.1

Preparing the installation site

13.1.1

Installation site requirements of the
outdoor unit

Mind the spacing guidelines. See the "Technical data" chapter.

CAUTION

Appliance not accessible to the general public, install it in a
secured area, protected from easy access.

This  unit,  both  indoor  and  outdoor,  is  suitable  for
installation 

in 

commercial 

and 

light 

industrial

environment.

NOTICE

This  equipment  is  compliant  with  Class  A  of  EN55032/
CISPR  32.  In  a  residential  environment  this  equipment
may cause radio interference.

13.2

Opening the unit

13.2.1

To open the outdoor unit

DANGER: RISK OF ELECTROCUTION

DANGER: RISK OF BURNING/SCALDING

11×

A

B

Once the front plate A is open, the electrical component box can be
accessed. See 

"13.2.2 To open the electrical component box of the

outdoor unit"

 [

4

 16].

For service purposes, the pushbuttons on the main PCB need to be
accessed.  To  access  these  pushbuttons,  the  electrical  component
box  cover  does  not  need  to  be  opened.  See 

"16.1.3  To  access  the

field setting components"

 [

4

 32].

To  install  the  water  piping  and  field  wiring,  front  plate  B  has  to  be
removed.

13.2.2

To open the electrical component box of
the outdoor unit

NOTICE

Do  NOT  apply  excessive  force  when  opening  the
electronic  component  box  cover.  Excessive  force  can
deform  the  cover,  resulting  in  entering  of  water  to  cause
equipment failure.

SW8

2

1

13.3

Mounting the outdoor unit

13.3.1

To provide the installation structure

Make  sure  the  unit  is  installed  level  on  a  sufficiently  strong  base  to
prevent vibration and noise.

800 mm

600 mm

516 mm

480 mm

660 mm

a

▪ Fasten the unit in place using four foundation bolts M12. It is best

to  screw  in  the  foundation  bolts  until  their  length  remains  20  mm
above the foundation surface.

20 mm

14

Piping installation

14.1

Preparing refrigerant piping

14.1.1

Refrigerant piping requirements

NOTICE

Refrigerant  R410A  requires  strict  cautions  for  keeping  the
system clean and dry. Foreign materials (including mineral
oils  or  moisture)  should  be  prevented  from  getting  mixed
into the system.

NOTICE

The  piping  and  other  pressure-containing  parts  shall  be
suitable  for  refrigerant.  Use  phosphoric  acid  deoxidised
seamless copper for refrigerant.

▪ Foreign materials inside pipes (including oils for fabrication) must

be ≤30 mg/10 m.

▪ Temper  grade:  use  piping  with  temper  grade  in  function  of  the

pipe diameter as listed in table below.

Pipe Ø

Temper grade of piping material

≤15.9 mm

O (annealed)

Summary of Contents for VRV IV RWEYQ-T9

Page 1: ...lation and operation manual VRV IV water cooled system air conditioner English Installation and operation manual VRV IV water cooled system air conditioner RWEYQ8T9Y1B RWEYQ10T9Y1B RWEYQ12T9Y1B RWEYQ1...

Page 2: ...8 19 20 21 22 23 24 25 Directivelor cu amendamentele respective Direktive z vsemi spremembami Direktiivid koos muudatustega Direktyvose su papildymais Direkt v s un to papildin jumos Smernice v platno...

Page 3: ...S vastaava kyll stysl mp tila M C Kylm aine N Varmuuspainelaitteen asetus P bar Valmistusnumero ja valmistusvuosi katso mallin nimikilpi Maxim ln p pustn tlak PS K bar Minim ln maxim ln p pustn teplot...

Page 4: ...s not spin 13 8 2 15 Symptom The display shows 88 13 8 2 16 Symptom The compressor in the outdoor unit does not stop after a short heating operation 13 8 2 17 Symptom The inside of an outdoor unit is...

Page 5: ...r reference guide Preparation of the installation reference data Detailed step by step instructions and background information for basic and advanced usage Format Digital files on http www daikineurop...

Page 6: ...carrying wires are tautened before the earth wire is in case the power supply is pulled loose from the stress relief CAUTION Do NOT perform the test operation while working on the indoor units When pe...

Page 7: ...ation CAUTION NEVER touch the internal parts of the controller Do NOT remove the front panel Some parts inside are dangerous to touch and appliance problems may happen For checking and adjusting the i...

Page 8: ...ices ventilate the room and contact the dealer where you purchased the unit Do not use the system until a service person confirms that the portion where the refrigerant leaks is repaired 4 About the s...

Page 9: ...ch 6 hours before operation 6 2 2 About cooling heating fan only and automatic operation Changeover cannot be made with a user interface whose display shows change over under centralised control refer...

Page 10: ...humidity in your room with minimal temperature decrease minimal room cooling The micro computer automatically determines temperature and fan speed cannot be set by the user interface The system does...

Page 11: ...ing for damage If damaged the unit may fall and result in injury NOTICE Do NOT wipe the controller operation panel with benzine thinner chemical dust cloth etc The panel may get discoloured or the coa...

Page 12: ...unit manual Malfunction Measure The system operates but cooling or heating is insufficient Check if air inlet or outlet of outdoor or indoor unit is not blocked by obstacles Remove any obstacles and m...

Page 13: ...stop Operation automatically restarts when the noise ceases 8 2 9 Symptom Noise of air conditioners Indoor unit A zeen sound is heard immediately after the power supply is turned on The electronic ex...

Page 14: ...b Installation manual and operation manual c Additional refrigerant charge label d Installation information sticker e Fluorinated greenhouse gases label f Multilingual fluorinated greenhouse gases la...

Page 15: ...ratures from 21 C DB to 32 C DB or 14 C WB to 25 C WB The ambient temperature around the unit should be above 0 C DB and below 40 C DB Relative humidity around the unit should be below 80 The water te...

Page 16: ...l the water piping and field wiring front plate B has to be removed 13 2 2 To open the electrical component box of the outdoor unit NOTICE Do NOT apply excessive force when opening the electronic comp...

Page 17: ...ery Determine the proper size using the following tables and reference figure only for indication In case of heat pump system A B B B C D F G E x y b a 3 1 2 4 5 1 2 VRV DX indoor unit 3 Branch select...

Page 18: ...ed on the total capacity of the connected indoor units only in case RA DX indoor units are connected Total capacity index of connected indoor units Piping outer diameter size mm Gas pipe Liquid pipe 2...

Page 19: ...ll the following restriction conditions A B C a c b A B C a To indoor units b Outdoor unit multi connecting piping kit first branch c Outdoor unit multi connecting piping kit second branch 14 2 Prepar...

Page 20: ...on the piping between this shut off valve and the outdoor unit for cleaning by chemicals For cleaning and water draining of the outdoor unit long period of non use or during non use in winter install...

Page 21: ...the design flow rate calculated by the hydronic engineer when designing the building system Correct valve selection is done when following conditions are met B C AND E A D For further selection requir...

Page 22: ...ay enter the machine 14 3 6 Using the stop valve and service port To handle the stop valve Take the following guidelines into account Make sure to keep the appropriate stop valves open during operatio...

Page 23: ...nect the vacuuming recovery unit through a manifold to the service port of all stop valves p p R410A N2 b c e a f g h d A C 1 D B a Pressure reducing valve b Nitrogen c Weighing scales d Refrigerant R...

Page 24: ...ant piping for example water may have entered the piping first carry out the vacuum drying procedure below until all moisture has been removed All piping inside the unit has been factory tested for le...

Page 25: ...for 1 hour the system may contain too much moisture In that case break the vacuum by pressurising with nitrogen gas to a gauge pressure of 0 05 MPa 0 5 bar and repeat steps 1 to 3 until all moisture h...

Page 26: ...additional 0 5 kg of refrigerant per outdoor unit In case of heat recovery system Formula R X1 22 2 0 37 X2 19 1 0 26 X3 15 9 0 18 X4 12 7 0 12 X5 9 5 0 059 X6 6 4 0 022 1 04 A C R Additional refriger...

Page 27: ...ks to each outdoor unit NOTICE The refrigerant charging port is connected to the piping inside the unit The unit s internal piping is already factory charged with refrigerant so be careful when connec...

Page 28: ...flow rate is correct If not stop the pump immediately and carry out troubleshooting 14 6 4 To insulate the water piping The outdoor water piping MUST be insulated to prevent condensation during heatin...

Page 29: ...g In case of heat recovery system B i a b f c f e g d c h j j i a Field power supply with earth leakage protector b Main switch c Earth connection d Outdoor unit e Indoor unit f User interface g BS un...

Page 30: ...es using finishing tape as shown in figure below b a f c d f e f a Liquid pipe b Gas pipe c Finishing tape d High pressure low pressure gas pipe e Transmission wiring F1 F2 f Insulator 15 6 To route a...

Page 31: ...e closed valve Select a flow switch contact of at least 15 V DC 1 mA Connect the flow switch to X2M terminals 5 and 6 In case of a multi outdoor unit system install one or more flow switches depending...

Page 32: ...ng the current field setting value is possible In general normal operation can be resumed without special intervention after changing field settings Some field settings are used for special operation...

Page 33: ...atus of the unit What How Changing and accessing the setting in mode 1 Once mode 1 is selected push BS1 one time you can select the wanted setting It is done by pushing BS2 Accessing the selected sett...

Page 34: ...m 3 Each unit has a pump valve pump is OFF when slave unit does not operate Minimum water flow rate limit control To change the minimum water flow rate limit of the variable flow system change the set...

Page 35: ...tion Check that the unit is properly installed to avoid abnormal noises and vibrations when starting up the unit Field wiring Be sure that the field wiring has been carried out according to the instru...

Page 36: ...s 17 4 To perform a test run 1 Close all front panels in order to not let it be the cause of misjudgement except the electrical component box inspection opening service cover 2 Make sure all field set...

Page 37: ...site publicly accessible The full set of latest technical data is available on the Daikin Business Portal authentication required 19 1 Service space Outdoor unit Make sure the space around the unit is...

Page 38: ...pressor Double tube heat exchanger Liquid receiver Thermistor 20 Disposal NOTICE Do NOT try to dismantle the system yourself dismantling of the system treatment of the refrigerant oil and other parts...

Page 39: ......

Page 40: ...4P452190 1D 2020 10 Copyright 2017 Daikin 4P452190 1 D 0000000 Verantwortung f r Energie und Umwelt...

Reviews: