5 Commissioning

Installation manual

14

RZAG71~Y1

Sky Air Alpha-series

4P485927-1 – 2017.04

4.6.2

To check the insulation resistance of the
compressor

NOTICE

If,  after  installation,  refrigerant  accumulates  in  the
compressor,  the  insulation  resistance  over  the  poles  can
drop,  but  if  it  is  at  least  1  MΩ,  then  the  unit  will  not  break
down.

▪ Use a 500 V mega-tester when measuring insulation.

▪ Do not use a mega-tester for low-voltage circuits.

1

Measure the insulation resistance over the poles.

If

Then

≥1 MΩ

Insulation resistance is OK. This procedure
is finished.

<1 MΩ

Insulation resistance is not OK. Go to the
next step.

2

Turn ON the power and leave it on for 6 hours.

Result: 

The  compressor  will  heat  up  and  evaporate  any

refrigerant in the compressor.

3

Measure the insulation resistance again.

5

Commissioning

NOTICE

NEVER  operate  the  unit  without  thermistors  and/or
pressure  sensors/switches.  Burning  of  the  compressor
might result.

5.1

Checklist before commissioning

Do NOT operate the system before the following checks are OK:

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor units

 are properly mounted.

In case a wireless user interface is used: The 

indoor unit

decoration panel

 with infrared receiver is installed.

The 

outdoor unit

 is properly mounted.

The following 

field wiring

 has been carried out according

to this document and the applicable legislation:

▪ Between the local supply panel and the outdoor unit

▪ Between the outdoor unit and the indoor unit (master)

▪ Between the indoor units

There are NO 

missing phases

 or 

reversed phases

.

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed  according  to  this  document,  and  have  not  been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

The 

insulation resistance

 of the compressor is OK.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

There are NO 

refrigerant leaks

.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

5.2

To perform a test run

This task is only applicable when using the BRC1E52 user interface.

▪ When  using  BRC1E51,  see  the  installation  manual  of  the  user

interface.

▪ When using BRC1D, see the service manual of the user interface.

NOTICE

Do not interrupt the test run.

INFORMATION

Backlight.

  To  perform  an  ON/OFF  action  on  the  user

interface,  the  backlight  does  not  need  to  be  lit.  For  any
other  action,  it  needs  to  be  lit  first.  The  backlight  is  lit  for
±30 seconds when you press a button.

1

Perform introductory steps.

#

Action

1

Open the liquid stop valve (A) and gas stop valve (B)
by removing the stem cap and turning
counterclockwise with a hex wrench until it stops.

A

B

2

Close the service cover to prevent electric shocks.

3

Turn ON power for at least 6 hours before starting
operation to protect the compressor.

4

On the user interface, set the unit to cooling operation
mode.

2

Start the test run.

#

Action

Result

1

Go to the home menu.

Cool

Set to

28

°C

2

Press at least 4 seconds.

The Service Settings menu
is displayed.

3

Select Test Operation.

Return

Setting

Service Settings                   1/3

Test Operation

Maintenance Contact

Field Settings

Demand

Min Setpoints Differential

Group Address

Summary of Contents for RZAG100M7Y1B

Page 1: ...Installation manual Sky Air Alpha series English Installation manual Sky Air Alpha series RZAG71M7V1B RZAG100M7V1B RZAG125M7V1B RZAG140M7V1B RZAG71M7Y1B RZAG100M7Y1B RZAG125M7Y1B RZAG140M7Y1B ...

Page 2: ...0 1000 1000 500 HD HU HU a b 100 100 c d e eB eD A B C D E HB HD A B C 200 300 1000 A B C E 200 300 1000 1000 500 D 1000 D E 1000 1000 500 B D HD HU 300 1000 HD HU 250 1500 HU HD HU 300 1500 B D E HB HD HB HU 300 1000 1000 500 HU HB HU 300 1250 1000 500 HB HU HB HD HD HU 250 1500 1000 500 HU HD HU 300 1500 1000 500 HD HU 1 b mm HB HU b 250 HU HB HU b 300 HB HU HB HU 1000 200 2000 100 3000 600 1500...

Page 3: ...ão em Директив со всеми поправками 10 11 12 13 14 15 16 17 Direktiver med senere ændringer Direktiv med företagna ändringar Direktiver med foretatte endringer Direktiivejä sellaisina kuin ne ovat muutettuina v platném znění Smjernice kako je izmijenjeno irányelv ek és módosításaik rendelkezéseit z późniejszymi poprawkami 18 19 20 21 22 23 24 25 Directivelor cu amendamentele respective Direktive z ...

Page 4: ...n suurin sallittu lämpötila TS TSmin Alhaisin matalapainepuolen lämpötila L C TSmax Suurinta sallittua painetta PS vastaava kyllästyslämpötila M C Kylmäaine N Varmuuspainelaitteen asetus P bar Valmistusnumero ja valmistusvuosi katso mallin nimikilpi Maximální přípustný tlak PS K bar Minimální maximální přípustná teplota TS TSmin Minimální teplota na nízkotlaké straně L C TSmax Saturovaná teplota o...

Page 5: ...ation 13 4 6 2 To check the insulation resistance of the compressor 14 5 Commissioning 14 5 1 Checklist before commissioning 14 5 2 To perform a test run 14 5 3 Error codes when performing a test run 15 6 Disposal 15 7 Technical data 16 7 1 Overview Technical data 16 7 2 Service space Outdoor unit 16 7 3 Piping diagram Outdoor unit 17 7 4 Wiring diagram Outdoor unit 17 1 About the documentation 1 ...

Page 6: ...m 150 6 2 0 350 3 4 5 3 5 5 4 M12 a a Make sure not to cover the drain holes of the bottom plate of the unit INFORMATION The recommended height of the upper protruding part of the bolts is 20 mm 20 NOTICE Fix the outdoor unit to the foundation bolts using nuts with resin washers a If the coating on the fastening area is stripped off the nuts rust easily a 4 1 2 To install the outdoor unit 4 M12 4 ...

Page 7: ...e cover a with screw b Remove the piping intake plate c with screw d c a b d 2 Choose a piping route a b c or d a b c d 3 If you have chosen the downwards piping route Drill a 4 and remove the knockout hole b Cut out the slits c with a metal saw c c b a 4 Ø6 mm 4 Do the following Connect the liquid pipe a to the liquid stop valve Connect the gas pipe b to the gas stop valve a b 5 Do the following ...

Page 8: ...at least 200 kPa 2 bar It is recommended to pressurize to 3000 kPa 30 bar in order to detect small leaks 2 Check for leaks by applying the bubble test solution to all connections 3 Discharge all nitrogen gas 4 3 3 To perform vacuum drying NOTICE Connect the vacuum pump to both the service port of the gas stop valve and the service port of the liquid stop valve to increase efficiency Make sure that...

Page 9: ...ing or recharging activate field setting vacuum mode After finishing vacuum drying or recharging deactivate field setting vacuum mode WARNING Some sections of the refrigerant circuit may be isolated from other sections caused by components with specific functions e g valves The refrigerant circuit therefore features additional service ports for vacuuming pressure relief or pressurizing the circuit...

Page 10: ...win triple and double twin 1 Determine G1 and G2 G1 m Total length of x liquid piping x Ø9 5 mm standard x Ø12 7 mm size up G2 m Total length of Ø6 4 mm liquid piping 2 Determine R1 and R2 If Then G1 40 m a Use the table below to determine R1 length G1 40 m a and R2 length G2 G1 40 m a and G1 G2 40 m a R1 0 0 kg Use the table below to determine R2 length G1 G2 40 m a a In case of size up Replace 4...

Page 11: ...ge 2 28 3 When 2 28 is reached press the BS3 button once 4 Change the setting to 1 by pressing the BS2 button once 5 Push the BS3 button once 6 When the display is not blinking anymore press the BS3 button again to activate vacuum mode To deactivate vacuum mode After charging or vacuuming the unit please deactivate the vacuum mode by changing the setting back to 0 Make sure to reattach the electro...

Page 12: ...A per phase RZAG71 140M7Y1B Equipment complying with EN IEC 61000 3 2 European International Technical Standard setting the limits for harmonic currents produced by equipment connected to public low voltage systems with input current 16 A per phase 4 5 2 Guidelines when connecting the electrical wiring Tightening torques Item Tightening torque N m M4 X1M 1 2 1 8 M4 earth 1 2 1 4 M5 X1M 2 0 3 0 M5 ...

Page 13: ...e Routing through the frame Choose one of the 3 possibilities a b a b a b 2 3 1 a Power supply cable b Interconnection cable Connecting to the frame When cables are routed from the unit a protection sleeve for the conduits PG insertions can be inserted at the knockout hole When you do not use a wire conduit protect the wires with vinyl tubes to prevent the edge of the knockout hole from cutting th...

Page 14: ...y earthed and the earth terminals are tightened The fuses or locally installed protection devices are installed according to this document and have not been bypassed The power supply voltage matches the voltage on the identification label of the unit There are NO loose connections or damaged electrical components in the switch box The insulation resistance of the compressor is OK There are NO dama...

Page 15: ... wiring error between power supply and outdoor unit between outdoor unit and indoor units between indoor unit and user interface The fuse on the outdoor unit PCB has blown out E3 E4 or L8 The stop valves are closed The air inlet or air outlet is blocked E7 There is a missing phase in case of three phase power supply units Note Operation will be impossible Turn OFF the power recheck the wiring and ...

Page 16: ...cles walls baffle plates E Obstacle roof a b c d e Minimum service space between the unit and obstacles A B C D and E eB Maximum distance between the unit and the edge of obstacle E in the direction of obstacle B eD Maximum distance between the unit and the edge of obstacle E in the direction of obstacle D HU Height of the unit HB HD Height of obstacles B and D 1 Seal the bottom of the installatio...

Page 17: ... for See note See note Outdoor Outdoor Indoor Indoor Upper Upper Lower Lower Fan Fan ON ON OFF OFF 2 Layout English Translation Layout Layout Front Front Back Back Position of compressor terminal Position of compressor terminal 3 Notes English Translation Notes Notes Connection X1M Indoor outdoor communication Earth wiring English Translation Field supply 1 Several wiring possibilities Protective ...

Page 18: ...Earth leakage circuit breaker 30 mA Q1E Overload protection R1 R8 A1P Y1 only Resistor R1T Thermistor air R2T Thermistor discharge R3T Thermistor suction R4T Thermistor heat exchanger R5T Thermistor heat exchanger middle R6T Thermistor liquid R7T Thermistor fin R8 A1P V1 only Resistor RC A1P Y1 only Signal receiver unit S1PH High pressure switch S1PL Low pressure switch SEG1 SEG3 7 segment display...

Page 19: ......

Page 20: ...4P485927 1 2017 04 Copyright 2017 Daikin 4P485927 1 0000000X ...

Reviews: