Trial Operation and Testing

1.

Trial operation and testing

1-1 Measure the supply voltage and make sure that it falls in the specified range.
1-2 Trial operation should be carried out in either cooling or heating mode.

For heat pump

• In cooling mode, select the lowest programmable temperature; in heating mode, select the highest programmable 

temperature.
1) Trial operation may be disabled in either mode depending on the room temperature.
2) After trial operation is complete, set the temperature to a normal level (26

°

C to 28

°

C in cooling mode, 20

°

C to 24

°

C in 

heating mode).

3) For protection, the system disables restart operation for 3 minutes after it is turned off.

For cooling only

• Select the lowest programmable temperature.

1) Trial operation in cooling mode may be disabled depending on the room temperature.
2) After trial operation is complete, set the temperature to a normal level (26

°

C to 28

°

C).

3) For protection, the unit disables restart operation for 3 minutes after it is turned off.

1-3 Carry out the test operation in accordance with the operation manual to ensure that all functions and parts, 

such as louver movement, are working properly.

• The air conditioner requires a small amount of power in its standby mode. If the system is not to be used for some 

time after installation, shut off the circuit breaker to eliminate unnecessary power consumption.

• If the circuit breaker trips to shut off the power to the air conditioner, the system will restore the original operation 

mode when the circuit breaker is opened again.

2.

Test items

Test items

Symptom

Check

Indoor and outdoor units are installed properly on solid bases.

Fall, vibration, noise

No refrigerant gas leaks.

Incomplete cooling/heating 
function

Refrigerant gas and liquid pipes and indoor drain hose extension are 
thermally insulated.

Water leakage

Draining line is properly installed.

Water leakage

System is properly earthed.

Electrical leakage

The specified wires are used for inter-unit wiring.

Inoperative or burn damage

Indoor or outdoor unit’s air inlet or outlet has clear path of air.
Stop valves are opened.

Incomplete cooling/heating 
function

Indoor unit properly receives remote control commands.

Inoperative

01_EN_3P203824-12L.fm  Page 11  Thursday, October 18, 2012  10:39 AM

Summary of Contents for RXS42K2V1B

Page 1: ...Split series Montaj k lavuzlar R410A Split serisi Installationsanleitung Split Baureihe R410A Manuel d installation S rie split R410A Montagehandleiding R410A Split systeem Manual de instalaci n Serie...

Page 2: ...USTRIES LTD Low Voltage 2006 95 EC Electromagnetic Compatibility 2004 108 EC 3SB64564 13E Shinri Sada Manager Quality Control Department DAIKIN TCF 015 N4 09 2010 RXS42J2V1B RKS42J2V1B KEMA Quality B...

Page 3: ...5 2 40 DAIKIN TCF 015 P9 09 2012 DEKRA Certification B V NB0344 74736 KRQ EMC97 4957 3SB65451 19F Shinri Sada Manager Quality Control Department RXS42K2V1B Machinery 2006 42 EC Electromagnetic Compati...

Page 4: ...3SB65451 4 fm Page 2 Thursday October 27 2011 4 49 PM...

Page 5: ...s If refrigerant gas leaks during installation ventilate the area immediately Toxic gas may be produced if the refrigerant comes into contact with fire After completing installation check for refriger...

Page 6: ...In coastal areas or other places with salty atmosphere of sulfate gas corrosion may shorten the life of the air conditioner 9 Since drain flows out of the outdoor unit do not place under the unit any...

Page 7: ...itional refrigerant required for refrigerant pipe exceeding 10m in length Be sure to add the proper amount of additional refrigerant Failure to do so may result in reduced performance The suggested sh...

Page 8: ...oor Unit Installation 1 Installing outdoor unit 1 When installing the outdoor unit refer to Precautions for Selecting the Location and the Outdoor Unit Installation Drawings 2 If drain work is necessa...

Page 9: ...e nuts to prevent damage to the flare nuts and gas leakage Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand Then tighten them fully with the torque wrenches Cut exactly...

Page 10: ...valve s service port 2 Fully open gauge manifold s low pressure valve Lo and completely close its high pressure valve Hi High pressure valve subsequently requires no operation 3 Do vacuum pumping and...

Page 11: ...dimensions as below 3 Use separate thermal insulation pipes for gas and liquid refrigerant pipes Gas side Liquid side Gas pipe thermal insulation Liquid pipe thermal insulation O D 9 5mm O D 6 4mm I D...

Page 12: ...l operation to stop press the indoor unit ON OFF switch Using the indoor unit s remote controller 1 Press MODE button and select the cooling mode 2 Press ON OFF button to turn on the system 3 Press bo...

Page 13: ...re the heat exchanger of the unit is exposed to direct wind provide a windbreak wall Intermittent noises may be produced by the indoor unit due to the outdoor fan turning on and off when using facilit...

Page 14: ...e systems with input current 16 A and 75 A per phase Observe the notes mentioned following when wiring to the power supply terminal board Precautions to be taken for power supply wiring Use a round cr...

Page 15: ...n in accordance with the operation manual to ensure that all functions and parts such as louver movement are working properly The air conditioner requires a small amount of power in its standby mode I...

Page 16: ...1210 HT 3P203824 12L M12B149 Two dimensional bar code is a code for manufacturing 00_CV_3P203824 12L fm Page 2 Thursday October 18 2012 10 38 AM...

Reviews: