background image

11

English

Trial Operation and Testing

1.

Trial operation and testing

1-1 Measure the supply voltage and make sure that it falls in the specified range.
1-2 Trial operation should be carried out in either cooling or heating mode.

• In cooling mode, select the lowest programmable temperature; in heating mode, select the highest programmable 

temperature.
1) Trial operation may be disabled in either mode depending on the room temperature.
2) After trial operation is complete, set the temperature to a normal level (26°C to 28°C in cooling mode, 20°C to 24°C 

in heating mode).

3) For protection, the system disables restart operation for 3 minutes after it is turned off.

1-3 Carry out the test operation in accordance with the operation manual to ensure that all functions and parts, 

such as louver movement, are working properly.

• The air conditioner requires a small amount of power in its standby mode.  If the system is not to be used for some 

time after installation, shut off the circuit breaker to eliminate unnecessary power consumption.

• If the circuit breaker trips to shut off the power to the air conditioner, the system will restore the original operation 

mode when the circuit breaker is opened again.

2.

Test items 

Test items

Symptom

Check

Indoor and outdoor units are installed properly on solid bases.

Fall, vibration, noise

No refrigerant gas leaks.

Incomplete cooling/heating 
function

Refrigerant gas and liquid pipes and indoor drain hose extension are 
thermally insulated.

Water leakage

Draining line is properly installed.

Water leakage

System is properly earthed.

Electrical leakage

The specified wires are used for inter-unit wiring.

Inoperative or burn damage

Indoor or outdoor unit’s air inlet or air outlet has clear path of air.
Stop valves are opened.

Incomplete cooling/heating 
function

Indoor unit properly receives remote control commands.

Inoperative

3PEN358184-2E.book  Page 11  Friday, October 23, 2015  10:54 AM

Summary of Contents for RXG50L2V1B

Page 1: ...rie split R410A Fran ais Montagehandleiding R410A Split systeem Nederlands Manual de instalaci n Serie Split R410A Espa ol Manuale d installazione Serie Multiambienti R410A Italiano R410A Manual de I...

Page 2: ...B de acuerdo con el Certificado C 06 Nota delineato nel A e giudicato positivamente da B secondo il Certificato C 07 A B C 08 Nota tal como estabelecido em A e com o parecer positivo de B de acordo c...

Page 3: ...en wiring the power supply and connecting the wiring between the indoor and outdoor units position the wires so that the control box lid can be securely fastened Improper positioning of the control bo...

Page 4: ...iling or stacked CAUTION When operating the air conditioner in a low outdoor ambient temperature be sure to follow the instructions described below To prevent exposure to wind install the outdoor unit...

Page 5: ...e and vibration may occur depending on how the unit is installed and the environment in which it is used When connecting the FVXG indoor unit the shortest piping length should be no less than about 2...

Page 6: ...Unit Installation 1 Installing outdoor unit 1 When installing the outdoor unit refer to Precautions for Selecting the Location and the Outdoor Unit Installation Drawings 2 If drain work is necessary...

Page 7: ...he flare nuts to prevent damage to the flare nuts and gas leakage Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand Then tighten them fully with the torque wrenches A A...

Page 8: ...h comes from gauge manifold to gas stop valve s service port 2 Fully open gauge manifold s low pressure valve Lo and completely close its high pressure valve Hi High pressure valve subsequently requir...

Page 9: ...and to provide insulation dimensions as below Use separate thermal insulation for gas and liquid refrigerant pipes Gas side Liquid side Gas pipe thermal insulation Liquid pipe thermal insulation O D...

Page 10: ...utdoor unit forced cooling operation switch is pressed within around 3 minutes after power is supplied Push on SW1 with a screwdriver The operation will start Forced cooling operation will stop automa...

Page 11: ...he screws Observe the notes mentioned below when wiring to the power supply terminal block Precautions to be taken for power supply wiring CAUTION When connecting the wires to the terminal block using...

Page 12: ...ser DISCHARGE Discharge C7 C8 Capacitor DB1 DB3 Diode bridge FU1 FU2 FU3 Fuse FU4 Field fuse IPM Intelligent power module L Live L803 L804 Reactor M1C Compressor motor M1F Fan motor MRCW MRM10 MRM20 M...