2

Caution

Ground the air conditioner.
Grounding resistance should be according to national
regulations
Do not connect the earth wire to gas or water pipes,
lightning conductor or telephone earth wire.
Incomplete grounding may cause electric shocks.

Gas pipe.
Ignition or explosion may occur if the gas leaks.

Water pipe.
Hard vinyl tubes are not effective grounds.

Lightning conductor or telephone ground wire.
Electric potential may rise abnormally if struck by a lightning
bolt.

Be sure to install an earth leakage breaker.
Failure to install an earth leakage breaker may cause electric
shocks and fire.

Install drain piping according to this installation manual to
ensure good drainage, and insulate the pipe to prevent
condensation.
Improper drain piping may cause water leakage, and make the
furnitures get wet.

Install the indoor and outdoor units, power wire and connecting
wire at least 1 meter away from televisions or radios to prevent
image interference or noise.
(Depending on the radio waves, a distance of 1 meter may not
be sufficient to eliminate the noise.)

Do not install the air conditioner in places such as the following:

Where there is mist of mineral oil, oil spray or vapor for
example a kitchen.
Plastic parts may deteriorate, and cause them to fall out or
water to leak.

Where corrosive gas, such as sulfurous acid gas, is
produced.
Corrosion of copper pipes or soldered parts may cause the
refrigerant to leak.

Where there is machinery which emits electromagnetic
waves.
Electromagnetic waves may disturb the control system, and
cause malfunction of the equipment.

Where flammable gases may leak, where carbon fiber or
ignitable dust is suspended in the air or where volatile
flammables, such as thinner or gasoline, are handled.
Such gases may cause a fire.

Where the air contains high levels of salt such as that near
the ocean.

Where voltage fluctuates a lot, such as that in factories.

In vehicles or vessels.

Where acidic or alkaline vapour is present.

B

EFORE

 

INSTALLATION

Precautions for R410A 

The refrigerant requires strict cautions for keeping the system
clean, dry and tight.
-

Clean and dry

Foreign materials (including mineral oils or moisture) should be
prevented from getting mixed into the system.
-

Tight

Read 

"Precautions on refrigerant piping" on page 5

 carefully and

follow these procedures correctly.

Since R410A is a mixed refrigerant, the required additional
refrigerant must be charged in its liquid state. (If the refrigerant
is in state of gas, its composition changes and the system will
not work properly).

The connected indoor units must be indoor units designed
exclusively for R410A.

Installation

For installation of the indoor unit(s), refer to the indoor unit
installation manual.

Illustrations show a class 125 outdoor unit type. Other types also
follow this installation manual.

This outdoor unit requires the pipe branching kit (optional) when
used as the outdoor unit for the simultaneous operation system.
Refer to catalogues for details.

Never operate the unit without the thermistor (R3T), burning of
the compressor may result.

Be sure to confirm the model name and the serial no. of the
outer (front) plates when attaching/detaching the plates to avoid
mistakes.

When closing the service panels, take care that the tightening
torque does not exceed 4.1 N•m.

Accessories

Check if the following accessories are included with the unit

Handling

As shown in the figure, bring the unit slowly by grabbing the left and
right grips. 

Place your hands on the corner instead of holding the suction inlet in
the side of the casing, otherwise the casing could be deformed.

Since design pressure is 4.15 MPa or 41.5 bar, pipes of
larger wall thickness may be required. Refer to 

"Selection

of piping material" on page 4

Fluorinated greenhouse gases 
label

1

Multilingual fluorinated 
greenhouse gases label

1

NOTE

Take care not to let hands or objects come in contact with
rear fins.

Summary of Contents for RQ100B8V3B

Page 1: ...INSTALLATION MANUAL RR71B8V3B RR71B2V3B RR100B8V3B RR71B8W1B RR71B2W1B RR100B8W1B RR125B8W1B RQ71B8V3B RQ71B2V3B RQ100B8V3B RQ71B8W1B RQ71B2W1B RQ100B8W1B RQ125B8W1B Split System air conditioners...

Page 2: ...1 2 4 5 2 4 5 9 7 6 6 8 3 3 1 3 2 4 5 A B A E B C D H H1 L1 H1 H2 L3 L1 L2 H1 H2 L4 L1 L3 L2 A A B2 B2 B2 C C D1 D1 D1 D2 D2 D2 D2 D2 E E H H L1 L1 L1 L2 L2 L2 A A B1 B1 B1 B1 B1 B1 B2 B2 B2 C C D1 D1...

Page 3: ...ttaen m r yksi 14 za dodr en ustanoven p edpisu 15 prema odredbama 16 k veti a z 17 zgodnie z postanowieniami Dyrektyw 18 n urma prevederilor 19 ob upo tevanju dolo b 20 vastavalt n uetele 21 22 laika...

Page 4: ...the power supply circuit or improper electrical construction may lead to electric shocks or fire Make sure that all wiring is secure using the specified wires and ensuring that external forces do not...

Page 5: ...contains high levels of salt such as that near the ocean Where voltage fluctuates a lot such as that in factories In vehicles or vessels Where acidic or alkaline vapour is present BEFORE INSTALLATION...

Page 6: ...e please install a waterproof plate within 150 mm of the underside of the unit in order to prevent the invasion of water from the lower direction 6 When installing the unit in a place frequently expos...

Page 7: ...ld comply with relevant local and national regulations The minimal pipe thickness for R410A piping must be in accordance with the table below O Annealed 1 2H Half hard Suction side obstacle Obstacle i...

Page 8: ...piping kit Install the branch pipes horizontally with a maximum inclination of 15 or vertically Length of branch pipe to the indoor unit should be as short as possible Try to keep lengths of both bra...

Page 9: ...e deformed if only a torque wrench is used when loosening or tightening flare nuts always lock the shut off valve with a wrench and then use a torque wrench Do not place wrenches on the valve cover Do...

Page 10: ...t coat the flare inner surface with ether oil or ester oil and initially tighten 3 or 4 turns by hand before tightening firmly After completing the installation carry out a gas leak inspection of the...

Page 11: ...rs and bring the system to 100 7 kPa After keeping the system under that condition for more than one hour check if the vacuum gauge rises or not If it rises the system may either contain moisture insi...

Page 12: ...mount R R1 R2 1 00 0 30 1 30 kg Example 2 1 G1 L1 5 m G2 L2 L3 L4 17 17 20 54 2 Over 30 m a G1 5 m R1 0 0 kg b G1 G2 30 5 54 30 29 6 4 R2 0 90 kg 3 Refrigerant charge amount R R1 R2 0 0 0 9 0 9 kg Tot...

Page 13: ...ground wire to the shut off valve attachment plate so that it does not slide 2 Secure the ground wire to the shut off valve attachment plate one more time along with the electric wiring and the inter...

Page 14: ...d wiring components Point for attention regarding quality of the public electric power supply This equipment complies with EN IEC 61000 3 11 1 provided that the system impedance Zsys is less than or e...

Page 15: ...For a missing phase in case of W1 units E0 or E6 will be displayed on the remote controller of the indoor unit Operation will be impossible with either one of these phenomena If this happens turn off...

Page 16: ...Q2M Thermo switch M1F M2F Q1RP Phase reverse circuit R1T Thermistor air R2T Thermistor coil R3T Thermistor discharge RC Signal receiver circuit S1PH Pressure switch HIGH S1PL Pressure switch LOW SD S...

Page 17: ...NOTES NOTES...