background image

English

13

English

Trial Operation and Testing

1.

Trial operation and testing

1-1 Measure the supply voltage and make sure that it falls in the specified range.
1-2 Trial operation should be carried out in either cooling or heating mode.

In cooling mode, select the lowest programmable temperature; in heating mode, select the highest programmable 
temperature.

1) Trial operation may be disabled in either mode depending on the room temperature.

Use the remote controller for trial operation as described below.

2) After trial operation is complete, set the temperature to a normal level (26°C to 28°C in cooling mode, 20°C to 24°C in 

heating mode).

3) For protection, the system disables restart operation for 3 minutes after it is turned off.

1-3 Carry out the test operation in accordance with the operation manual to ensure that all functions and parts, 

such as louvres movement, are working properly.

• The air conditioner requires a small amount of power in its standby mode.  If the system is not to be used for some 

time after installation, shut off the circuit breaker to eliminate unnecessary power consumption.

• If the circuit breaker trips to shut off the power to the air conditioner, the system will restore the original operation 

mode when the circuit breaker is opened again. 

2.

Test items 

Test items

Symptom

Check

Indoor and outdoor units are installed properly on solid bases.

Fall, vibration, noise

No refrigerant gas leaks.

Incomplete cooling/heating 
function

Refrigerant gas and liquid pipes and indoor drain hose extension are 
thermally insulated.

Water leakage

Draining line is properly installed.

Water leakage

System is properly earthed.

Electrical leakage

The specified wires are used for inter-unit wiring.

Inoperative or burn damage

Indoor or outdoor unit’s air inlet or air outlet has clear path of air.
Stop valves are opened.

Incomplete cooling/heating 
function

Indoor unit properly receives remote control commands.

Inoperative

1) Press “ON/OFF” button to turn on the system.
2) Press “TEMP” button and “MODE” button at the same time.
3) Press “TEMP” button and select “    ”.
4) Press “MODE” button.
5) Trial operation terminates in approx. 30 minutes and switches into normal mode. To quit a trial operation, press 

“ON/OFF” button.

Trial operation from remote controller

Summary of Contents for FTXJ20MV1BS

Page 1: ...R32 Split Series INSTALLATION MANUAL DAIKIN ROOM AIR CONDITIONER MODELS FTXJ20MV1BW FTXJ20MV1BS FTXJ25MV1BW FTXJ25MV1BS FTXJ35MV1BW FTXJ35MV1BS FTXJ50MV1BW FTXJ50MV1BS...

Page 2: ...nte por B de acuerdo con el Certificado C 06 Nota delineato nel A e giudicato positivamente da B secondo il Certificato C 07 A B C 08 Nota tal como estabelecido em A e com o parecer positivo de B de a...

Page 3: ...lead as this may cause overheating electric shocks or fire Make sure that all wiring is secured the specified wires are used and that there is no strain on the terminal connections or wires Improper c...

Page 4: ...troller signals are properly received by the indoor unit within 6m CAUTION Do not install the air conditioner at any place where there is a danger of flammable gas leakage In the event of a gas leakag...

Page 5: ...finishing tape from bottom to top Cut thermal insulation pipe to an appropriate length and wrap it with tape making sure that no gap is left in the insulation pipe s cut line Caulk pipe hole gap with...

Page 6: ...e front panel locks on the back of the front panel upward to release the locks left and right sides 2 Insert the panel shafts on both sides of the upper front panel into the shaft holes 3 Slide the fr...

Page 7: ...6 Install the air filter and then mount the upper front panel 3 How to set the different addresses When two indoor units are installed in one room the two wireless remote controllers can be set for di...

Page 8: ...e cutter 2 Remove burrs with the cut surface facing downward so that the chips do not enter the pipe 3 Put the flare nut on the pipe 4 Flare the pipe 5 Check that the flaring is properly made WARNING...

Page 9: ...Choose heat insulation materials that will withstand this temperature 2 Be sure to insulate both the gas and liquid piping and to provide insulation dimensions as below 3 Use separate thermal insulat...

Page 10: ...the upper front panel then remove the service lid 2 Pass the inter unit wire from the outdoor unit through the feed through wall hole and then through the back of the indoor unit Pull them through the...

Page 11: ...ant pipes and drain hose together with insulation tape as shown in the figure on the right in case of setting the drain hose through the back of the indoor unit Left back piping Right back piping Bind...

Page 12: ...nit side Apply the blade of the copping saw to the notch and cut off the pipe port cover along the uneven inner surface 2 After cutting off the pipe port cover perform filing Remove the burrs along th...

Page 13: ...for the drain pump etc from the terminal block Doing so may cause electric shock or fire Do not connect the indoor unit to the mains electricity Connect it to the outdoor unit only or there may be dan...

Page 14: ...circuit board BZ Buzzer FG Frame ground F1U F2U Fuse H1P H2P Pilot lamp M1F Fan motor M1S M2S M3S Swing motor M1 Stepping motor R1T R2T Thermistor S25 S200 Connector S1C Limit switch S1W Operation sw...

Page 15: ...llation shut off the circuit breaker to eliminate unnecessary power consumption If the circuit breaker trips to shut off the power to the air conditioner the system will restore the original operation...

Page 16: ...3P393185 6K 2015 11 Copyright 2015 Daikin...

Reviews: