7-5 HEAT INSULATION WORK
•
After the gas leakage inspection of piping joints, refer to Fig. 3 and Fig. 4 and conduct heat insula-
tion work on the joints.
• Use insulation for fitting (3) to conduct the heat insulation work.
(Refer to Fig. 3)
The heat insulation mate-
rial is provided to the liquid and gas pipes, respectively.
• Be sure to set the seam of the insulation for fitting (3) upward.
Use a clamp (2) to tighten both ends of the insulation for fitting.
(Refer to Fig. 4)
Attached to the root
Insulation for fitting (3)
(accessory)
Insulation for fitting (3)
(accessory)
Attached to the root
Heat insulation material for
piping (field supplied)
Heat insulation material for
piping (field supplied)
Heat insulation material
for piping (unit side)
Heat insulation material
for piping (unit side)
Fig. 3
Set the seam upward.
Clamp (2) (accessory)
Tighten the portion that overlaps with
heat insulation material for piping.
Fig. 4
Cut the marginal ends off after tightening.