Trial Operation and Testing

1.

Trial operation and testing

1-1 Measure the supply voltage and make sure that it falls in the specified range.
1-2 Trial operation should be carried out in either cooling or heating mode.

• In cooling mode, select the lowest programmable temperature; in heating mode, select the highest programmable 

temperature.
1) Trial operation may be disabled in either mode depending on the room temperature.
2) After trial operation is complete, set the temperature to a normal level (26°C to 28°C in cooling mode, 20°C to 24°C 

in heating mode).

3) For protection, the system disables restart operation for 3 minutes after it is turned off.

1-3 Carry out the test operation in accordance with the operation manual to ensure that all functions and parts, 

such as louver movement, are working properly.

• The air conditioner requires a small amount of power in its standby mode.  If the system is not to be used for some 

time after installation, shut off the circuit breaker to eliminate unnecessary power consumption.

• If the circuit breaker trips to shut off the power to the air conditioner, the system will restore the original operation 

mode when the circuit breaker is opened again.

2.

Test items 

Test items

Symptom

Check

Indoor and outdoor units are installed properly on solid bases.

Fall, vibration, noise

No refrigerant gas leaks.

Incomplete cooling/heating 
function

Refrigerant gas and liquid pipes and indoor drain hose extension are 
thermally insulated.

Water leakage

Draining line is properly installed.

Water leakage

System is properly earthed.

Electrical leakage

The specified wires are used for inter-unit wiring.

Inoperative or burn damage

Indoor or outdoor unit’s air inlet or air outlet has clear path of air.

Incomplete cooling/heating 
function

Stop valves are opened.

Incomplete cooling/heating 
function

Indoor unit properly receives remote control commands.

Inoperative

Summary of Contents for ARXS35L2V1B

Page 1: ...ion S rie split R410A Fran ais Montagehandleiding R410A Split systeem Nederlands Manual de instalaci n Serie Split R410A Espa ol Manuale d installazione Serie Multiambienti R410A Italiano R410A Manual...

Page 2: ...es valorado positivamente por B de acuerdo con el Certificado C 06 Nota delineato nel A e giudicato positivamente da B secondo il Certificato C 07 A B C 08 Nota tal como estabelecido em A e com o pare...

Page 3: ...ce en A y es valorado positivamente por B de acuerdo con el Certificado C 06 Nota delineato nel A e giudicato positivamente da B secondo il Certificato C 07 A B C 08 Nota tal como estabelecido em A e...

Page 4: ...rmal heat build up or fire When wiring the power supply and connecting the wiring between the indoor and outdoor units position the wires so that the control box lid can be securely fastened Improper...

Page 5: ...om ceiling or stacked CAUTION When operating the air conditioner in a low outdoor ambient temperature be sure to follow the instructions described below To prevent exposure to wind install the outdoor...

Page 6: ...the stop valve cover Remove the screw on the stop valve cover Slide the lid downward to remove it How to attach the stop valve cover Insert the upper part of the stop valve cover into the outdoor uni...

Page 7: ...e foundation surface Outdoor Unit Installation 1 Installing outdoor unit 1 When installing the outdoor unit refer to Precautions for Selecting the Location and the Outdoor Unit Installation Drawings 2...

Page 8: ...rque wrenches when tightening the flare nuts to prevent damage to the flare nuts and gas leakage Align the centres of both flares and tighten the flare nuts 3 or 4 turns by hand Then tighten them full...

Page 9: ...x Choose heat insulation materials that will withstand this temperature 2 Be sure to insulate both the gas and liquid piping and to provide insulation dimensions as below 3 Use separate thermal insula...

Page 10: ...f charging hose which comes from gauge manifold to gas stop valve s service port 2 Fully open gauge manifold s low pressure valve Lo and completely close its high pressure valve Hi High pressure valve...

Page 11: ...3 Disconnect the selective connector for standby electricity saving 4 Turn on the main power supply CAUTION Before connecting or disconnecting the selective connector for standby electricity saving ma...

Page 12: ...n pressing the switch do not touch the terminal block It has a high voltage so doing so may cause electric shock After closing the liquid stop valve close the gas stop valve within 3 minutes then stop...

Page 13: ...block Observe the notes mentioned below when wiring to the power supply terminal block Precautions to be taken for power supply wiring CAUTION When connecting the connection wires to the terminal blo...

Page 14: ...R Outdoor CONDENSER Condenser DISCHARGE Discharge C7 C8 Capacitor DB1 DB3 Diode bridge FU1 FU2 FU3 Fuse FU4 Field fuse IPM Intelligent power module L Live L803 L804 Reactor M1C Compressor motor M1F Fa...

Page 15: ...a small amount of power in its standby mode If the system is not to be used for some time after installation shut off the circuit breaker to eliminate unnecessary power consumption If the circuit brea...

Page 16: ...3P360062 2C 2013 11 Copyright 2013 Daikin...

Reviews: