6 of 8
LPN00644X0007A0_A
SECTION 3:
OFF GRID MOUNTING (HARD CEILING) -
INDIVIDUAL RECESSED MOUNTING
CAUTION:
Ceiling contractor must provide an uninterrupted,
continuous rough opening. Dimensions of opening should be
determined using
Figure 3 on page 3 and Figure 9.
CAUTION:
Luminaires should be secured to structure above
using customer supplied threaded rods to support weight of
luminaire.
STEP 1:
Remove lens and LED/reflector tray and set aside in order
of run placement for reinstalling later. To remove lens,
carefully slide a plastic card or putty knife between the lens
and extrusion towards the end of the luminaire. Using the
plastic card or putty knife, push the lens inward until the
lens come free. After removing the lens, remove the Philips
head reflector screws, remove the LED Reflector Tray, and
disconnect the LED harness. Set lens and LED Reflector tray
aside. See
Figure 2 and 8.
STEP 2:
Using one of the 7/8" dia. holes on the end of the fixture,
install conduit connector. See
Figure 8.
STEP 3:
Install fixture from below into ceiling opening. Attach
customer supplied threaded rods to luminaire through 5/8"
mounting holes located on the top of the housing and to the
structure above as shown in
Figure 8
. Confirm that fixture is
pulled up firm to ceiling line.
STEP 4:
Make electrical connections per Section 5 “Electrical
Connections” to leads in wiring compartment.
STEP 5:
Reconnect LED harness. Replace LED trays and lens that
was removed in Step 1 above, ensure that no wires are
pinched.
STEP 6:
For Hard Ceiling, Overlap Flange Only:
Fill in Sheet Rock mud over tapered extruded flange until
smooth. See
Figure 10.
9
4.25"
Ceiling opening width
for Flangeless
3.37"
Ceiling opening width
overlapping flange
8
Flexible Conduit
Supplied By Others
Threaded Support Rods Supplied By Others
Support Nut
Supplied By Others
LED Tray
Lens
#10-18 X 1/4”
Phillips Head Screws
Sheetrock Mud
Supplied By Others
Sheetrock Mud
Supplied By Others
Threaded Support Rod
Supplied by Others
10