VCIOM-05044
Page 60 of 75
DIgITal EPIC-2 TEChnICal Manual
InstallatIon and operatIng InstructIons
From PST Sign Sub-menu, scroll down
to “gen new PST” then press SElECT.
From PST Sign Sub-menu, scroll down to
“View all PST” then press SElECT.
From gen new PST sub-menu, scroll to “Start
MPST” to generate a new Maintenance PST,
then press EnTER.
7.3.4.3.2.1.2 Generate maintenance PST
7.3.4.3.2.2 View PST data
The Maintenance PST should now proceed. The
screen will update the % Done until it reaches
100%. The user has the option of aborting by
simultaneously pressing the up and Down
arrow keys.
Once the PST completes, if successful, the
screen above will appear. If the PST failed, the
screen will show the failure reason on screen.
The reason for the failure must be resolved and
perform the test again. Finally, press SElECT/
EnTER key to exit back to previous sub-menu.
next you will be asked if you want to continue,
use the Down arrow key to select between “no”
or “Yes” then press EnTER. If no is selected,
the PST will not be done and will return to
the previous sub-menu. If Yes is selected the
Baseline PST will start.
Copyright © Crane Co. All rights reserved.