Step 21: START UP PRE-CHECKLIST
Prior to performing an electrical and hydraulic performance check of the complete station, verify all of the following
criteria are met:
The shut-off and redundant check valve at force main are installed in the lateral discharge and are in the open
position
Discharge piping has been pressure tested to 150 PSI max without leakage
Inlet has a minimum of 1/8” per foot drop
All penetrations through basin and electrical enclosure sealed water-tight
Proper backfill and compaction has been done to prevent deflection or possible failure of equipment
All cords are secured and clear of pump cutter and level control
Electrical supply is of proper voltage, phase for the pump
A properly sized double pole circuit breaker has been installed in the service disconnect panel
Proper gauge and conductor wire installed from service disconnect to house panel
All terminal connections are secure
Circuit breakers in the Alarm Box are turned to the “OFF” position
Circuit breaker in the service disconnect turned to “ON”
Pump is properly seated on the discharge opening in the rail
Level control is installed properly
Final grade slopes away from the basin to avoid runoff water collection/ basin inflow
All construction and shipping debris has been removed from the basin
Step 22: START-UP CHECKLIST
Water has been added to the basin to a level of approximately 1” above the pump support flange
Valve(s) within the basin and lateral are in the “OPEN” position (Pull on Green Strap in station)
Record pump and basin nameplate information on the start-up form (Before installing pump)
All alarm devices are turned to the “ON” position
Complete START-UP check sheet located in the back of the manual
Summary of Contents for Barnes EcoTRAN
Page 6: ...6 PACKAGED PARTS AS RECEIVED ...
Page 10: ...10 STEP 4 SETTING THE BASIN Location Overview ...
Page 11: ...11 STEP 5 RISER TANK PARTS ASSEMBLY ...
Page 32: ...32 ...
Page 34: ...Notes ...