Standard Recommended Procedure 206-455-AEN | Issue 1 | November 2018 | Page 7 of 14

10.  Load Express Fibers

IMPORTANT: 

Basic ribbon fiber routing requires Ribbon “A” spliced to Ribbon “B.” Ribbon “B” will be routed to 

the side of the splice plane opposite from Ribbon “A.”

• 

For sub-ribbon splicing, split the ribbon matrix with appropriate equipment (P/N RST-000 

or equivalent) and separate ribbon matrix within 6 in of cable sheath opening. Secure this 

separation point with tape.

Step 1: 

Form the subunits from each cable into a single slack loop placed into the middle storage 

compartment of the frame 

(Figure 14)

 and cover. Route the extra length toward the side storage 

compartments.

NOTE: 

Do not yet route any fibers or subunits in the side storage compartment, but rather let subunit lay free 

until splicing each subunit.

Figure 14

TPA-6314

Express cable

Figure 13 

TPA-6366

Summary of Contents for SCF-1296

Page 1: ...ed Procedures Figure 1 TPA 6313 Table of Contents 1 General 2 2 Tools and Materials 2 3 Carton Contents 2 4 Prepare the Cable 2 5 Prepare End Cap 4 6 Continue Cable Preparation 4 7 Install Strain reli...

Page 2: ...heat shink tube branching clip and UCN lubricant 4 Prepare the Cable CAUTION The wearing of cut resistant safety gloves to protect your hands from accidental injury when using sharp bladed tools and...

Page 3: ...o cable manufacturer s instructions Figure 2 IMPORTANT Do not expose the bare fibers until after the cable has been placed in the closure end cap Do not untwist the subunits or remove their jacketing...

Page 4: ...n 7 mm 28 in min N A 41 4 mm 1 65 in max 28 mm 1 10 in max 32 5 mm 1 29 in max 15 5 mm 60 in max 12 7 mm 58 in max N A Figure 5 a Carefully tap the end using a punch or a nut driver Figure 6 b Clean t...

Page 5: ...a immediately with soap and water to avoid irritation Do not induce vomiting if paste or cleaner is ingested IMPORTANT Torches are not recommended for the application of the heat shrink tubes included...

Page 6: ...le 9 Attach Frame to End Cap Step 1 Remove splice plane and slack storage covers Section Figure 12 Figure 12 Step 2 Secure the end cap on the work surface table with the express cable to the top Step...

Page 7: ...pment P N RST 000 or equivalent and separate ribbon matrix within 6 in of cable sheath opening Secure this separation point with tape Step 1 Form the subunits from each cable into a single slack loop...

Page 8: ...er s tape NOTE Only use the ribbon splitting tool on the first two to four inches of ribbon Clean excess ribbon matrix from the tool often Split the rest of the ribbon length by hand Step 5 Create a l...

Page 9: ...d splice a To ensure the appropriate length of slack fibers cut the fibers extending beyond the bottom of the closure as shown in Figure 20 b Remove the tape from the fibers c Remove the fibers from t...

Page 10: ...ices Install the second splice on top of the first splice before proceeding to the next slot in the organizer Step 5 Secure the spliced ribbons in the clips on the splicing plane Confirm the fibers do...

Page 11: ...etained previously to the threads of the clamping ring latch bolts to prevent the bolts from seizing on reentry Step 4 Place the clamping ring over the flange of the canister and the sealing ring Ensu...

Page 12: ...sure with no leaks Step 3 After the flash test has been performed and the closure sealed correctly carefully remove the air valve and allow air to escape 14 Ground the Closure Optional Step 1 Apply a...

Page 13: ...h member is metal bend it over the slots in the extension bracket as shown in the inset in Figure 30 and then trim excess strength member Step 5 Wrap the strength member yarn around the restraint cap...

Page 14: ...Optical Communications is available at www corning com opcomm trademarks All other trademarks are the properties of their respective owners Corning Optical Communications is ISO 9001 certified 2018 C...

Reviews: