Apricus Installation Manual
52
Flow Valve. The Flow rate can be read on the
sight glass.
Remove the flush & fill hoses from the
pumping station and attach closing caps
onto the valves to seal them.
Re-Check System for leaks.
Ensure all valves are in operational positions.
Ensure Solar Controller is set to Automatic
Operation.
Post Installation
Collector Operation
Once all the tubes are installed and the
system is fully commissioned, the solar
collector will begin to produce heat after a
5-10 minute warm up period when the sun
is shining. Check the controller and pump for
correct operation and adjust settings as
required. Make sure that you have changed
the controller setting from ON to
AUTOMATIC.
Clean Up
Once the system is confirmed as operating
correctly, ensure the installation site is
cleaned of all rubbish that should be
recycled, whenever possible.
Chemicals, paints and heat transfer fluids
must be disposed of in line with their MSDS
guidelines provided by the manufacturer and
in line with local regulations.