background image

Page  10

 

 

When installing Water shortage protection Type RT 200 Pressostat, the installation engineer must 
adjust the pressostat so that it stops the system, when the operational pressure is below 0.5 bar over 
pressure. Furthermore, the installation engineer must test that the pressostat physically stops the 
system when the operational pressure < 0.5. This is done by filling the system to more than 0.5 bar 
over pressure, starting the system and shut off the water supply until the system stops; this should 
happen at 0.5 bar over pressure.

 

 

 

Maintenance and cleaning: 

 
 

 

The closing mechanisms of the door and cleaning hatch are adjusted from the factory but must be 
inspected for correct sealing after a month of use, when the gasket has ”settled”. 

 

 

 

If any irregularities are found in the safety valve(s), expansion vessel or automatics of the unit, the 
owner/user must immediately have the equipment in question inspected and repaired by an 
authorised engineer. The owner/user must ensure that any installed safety valves are not blocked by 
scale etc. It is the responsibility of the owner/user that the boiler and any equipment is cleaned and 
maintained according to: 

 

Normal practice,

 

 

The boiler flue system is cleaned by opening the top hatch of the boiler. The many flue pipes placed 
at the top of the boiler should be cleaned every 3 days with the round cleaning brush/cleaning tool 
supplied with the boiler. Push the brush all the way through; take care not to damage the bottom tile 
in the smoke box. Pull the brush / cleaning tool back out; repeat several times for each pipe. After 
cleaning, empty the smoke box at the back of the boiler. The boiler must always be switched off 
during cleaning. Clean smoke pipes and smoke box result in more economical operation. 

 

The boiler combustion chamber should be cleaned every 24 hours (of use). 

 

If the boiler is switched off for a long period (approximately 1 week), the boiler and flue pipes should 
be cleaned thoroughly, as the residue combined with damp results in corrosion

 

The pump(s) must be switched off whilst the system is filled up with water 

 

NOTE: Do not fill up an overheated boiler with water. 

 

Installation with pressure expansion: water filling until 1.5-2.0 bar. 

 

Installation with open expansion: water filling until the water runs out of the expansion vessel 
overflow. 

 

Testing the safety valves

: It is the responsibility of the user that the installed safety valves are 

tested twice annually. This is done by pressing or turning the valve test device. By doing this you are 
able to see and hear a bit of water being released and thereby confirm that the valve is operational. 
Damages caused by a blocked safety valve are not covered by the warranty issued by CN 
MASKINFABRIK A/S. 

 

Safety valves are installed in connection with the central heating unit (2.5 bar) and possibly in 
connection with the hot water circuit (6 bar or 10 bar). Please ask your installation engineer if in doubt 
about the location of the valves. 

 

After 300 hours’ operation, nuts and bolts must be tightened and doors adjusted! 

 

Replacing the glass string in doors 

 

 

Open the door. Remove the old gasket, if necessary with a chisel or a screw driver. Clean the gasket 
groove. Push the new gasket into the groove. Put the last end in place when this is about half done, 
and then the rest. Bang the string lightly with a hammer if necessary.   

 

Frost protection: 

 

During normal operation above freezing point there is no need for frost protection. 

 

The central heating unit can be protected with anti-freeze solution. Remember, however, that the hot 
water container, if relevant, is not protected against frost. 

 

When stopping the unit at an ambient temperature below zero, the boiler must be emptied of water. 
This is done by running a hose from the bottom tap of the boiler to a drain in the floor and opening 
the tap. 

 
 

Summary of Contents for 120

Page 1: ...Page 1 User Manual for CN Boilers Type 80 120 Machine no Date CN Maskinfabrik A S Skovløkkevej 4 Tiset 6510 Gram Denmark Tel 74 82 19 19 Fax 74 82 19 20 Version April 2005 ...

Page 2: ...nty Claims Page 12 Check List End User Page 13 Check List Supplier Page 14 Check List CN MASKINFABRIK A S Page 15 Warranty Certificate Customer Copy Page16 5 Year Warranty Certificate CN MASKINFABRIK A S Page 17 Principle Diagram Overflow Valve Cooling Spiral Page 18 Principle Diagram Open Expansion with Accumulation Tank Page 19 Principle Diagram Pressure Expansion Without Accumulation Tank Page ...

Page 3: ... surrounded by water The construction and dimensions of the CN boiler thus create an efficient use of the smoke gas before it reaches the smoke outlet The large doors of the CN boiler which open both the fire chamber and the smoke ducts make cleaning the boiler very efficient and easy Optimal environmentally friendly and highly efficient burning of the wood requires correct ratio between the combu...

Page 4: ...480 I mm 980 1180 J Supply Return inches 2 2 L Expansion vessel inches 1 1 M Flue regulator inches 1 1 Yield wood kW 65 100 Yield automatic stoking kW 80 120 Heat surface m2 7 5 9 6 Volume fire chamber m2 0 75 1 07 Test pressure bar 4 4 Water content litre 490 560 Fire box diameter mm 815 970 Fire box depth mm 1450 1450 Smoke tube stub diameter mm 250 250 ...

Page 5: ...illingness and correct attitude to burning wood as it does after all take a bit of work to yield the crops of this environmentally friendly and financially profitable type of heating Safety If any faults or failures are found they must be repaired as soon as possible by a boiler engineer Flue pipes ventilation ducts air holes etc must not be closed off or blocked Flammable liquids or combustible s...

Page 6: ...ave an uphill gradient of minimum 1 and all joints must be tight Never use a smaller diameter smoke pipe as the boiler outlet pipe Always use elbows with a bending and flap as bent joints as they provide the best flue All smoke pipes must be insulated also when the boiler is used with stoker feeding The combustion must not be carried out until the boiler is installed and fully connected A probe mu...

Page 7: ...t the boiler unit must fulfil certain essential safety requirements regarding the safety equipment of the boiler etc The boiler must be fitted with a cooling spiral Expansion vessel The vessel must be installed in accordance with the directions of The Health and Safety at Work Act 1974 The bottom of the expansion vessel should be installed only above pipes radiator of the central heating system an...

Page 8: ...e NTC 2322 2 CN supplied with stoker Overheating thermostat Honeywell type L6188 3 CN supplied with stoker Boiler thermometer 0 120 degrees 4 Installation engineer Pressure gauge manometer 0 3 maximum 5 bar red marks at 2 5 bar 4 Installation engineer Pressure expansion vessel CE labeled minimum 4 of total system water volume see table below 6 Installation engineer Safety valve CE approved 2 pces ...

Page 9: ...ostat BS components type 2322 2 CN supplied with stoker Overheat thermostat Honeywell type L6188 3 CN supplied with stoker Boiler thermometer 0 120 C degrees 4 Installation engineer Pressure gauge manometer 0 3 maximum 5 bar red mark at 2 5 bar 4 Installation engineer Accumulation tank Type approved in acc with Declaration on Installation of Pressurised Equipment 11 Installation engineer Shunt val...

Page 10: ...ed every 24 hours of use If the boiler is switched off for a long period approximately 1 week the boiler and flue pipes should be cleaned thoroughly as the residue combined with damp results in corrosion The pump s must be switched off whilst the system is filled up with water NOTE Do not fill up an overheated boiler with water Installation with pressure expansion water filling until 1 5 2 0 bar I...

Page 11: ...iler thermostat setting range is 55 85 C Water content in 80 120 boiler 490 560 L Boiler classification 3 Set point for boiler thermostat 65 C Warranty Claims CN MASKINFABRIK A S provides a 24 month warranty for the stoker unit following the date of this user manual for the first user The warranty includes materials and manufacturing faults but not wear on parts damages caused by failure to mainta...

Page 12: ...ve received instructions in the maintenance of the boiler Boiler type Serial number Year I hereby declare that I have understood the received material Name ____________________________________ Address ____________________________________ Town and post code ____________________________________ ____________________________________ Signature For End user ...

Page 13: ...eived instructions in the maintenance of the boiler Boiler type Serial number Year I hereby declare that I have understood the received material Name ____________________________________ Address ____________________________________ Town and post code ____________________________________ ____________________________________ Signature Please return to Supplier ...

Page 14: ...rtificate______________ The installation engineer has subjected the boiler unit to a construction test module B1 or installed the boiler unit in accordance with a full quality assurance system module H in accordance with the Pressure Equipment Directive 97 23 EEC _____________________ Boiler type Serial number Year I hereby declare that I have understood the received material Name ________________...

Page 15: ...MASKINFABRIK A S 5 The boiler must a no time have been used for burning grain 6 The boiler must not be exposed to insufficient maintenance incorrect use or overloading 7 CN MASKINFABRIK A S will repair any claims or approve the repair before it is carried out according to the choice of CN The service includes the following Gaskets inspected and checked Doors inspected tightened and adjusted Boiler...

Page 16: ...overloading 7 CN MASKINFABRIK A S will repair any claims or approve the repair before it is carried out according to the choice of CN The service includes the following Gaskets inspected and checked Doors inspected tightened and adjusted Boiler cleaned and inspected Installation inspected Smoke pipe inspected and checked Any fire resistant materials inspected and checked Cleaning tools inspected a...

Page 17: ...Page 17 ...

Page 18: ...Page 18 MASKINFABRIK A S Skovløkkevej 4 Tiset 6510 Gram Tlf 74 82 19 19 MASKINFABRIK A S Skovløkkevej 4 Tiset 6510 Gram Tlf 74 82 19 19 Check valve Draining ...

Page 19: ...SKINFABRIK A S Skovløkkevej 4 Tiset 6510 Gram Tlf 74 82 19 19 This drawing is a principle diagram Hence CN Maskinfabrik A S cannot be made responsible for faults errors or losses based on this diagram Check valve ...

Page 20: ...SKINFABRIK A S Skovløkkevej 4 Tiset 6510 Gram Tlf 74 82 19 19 This drawing is a principle diagram Hence CN Maskinfabrik A S cannot be made responsible for faults errors or losses based on this diagram Check valve ...

Page 21: ...SKINFABRIK A S Skovløkkevej 4 Tiset 6510 Gram Tlf 74 82 19 19 This drawing is a principle diagram Hence CN Maskinfabrik A S cannot be made responsible for faults errors or losses based on this diagram Check valve ...

Reviews: