1943052
V1.3
June 2019
Clevertest and Clevertest Plus
Refer to the supplementary operation guide supplied with the Product.
After Power ON, the Status LED on a Clevertest Plus enabled fitting will display a rapid Green or
Red flashing for a period up to 2 minutes.
Zoneworks and DATA Monitored Options
Ultrablades with part numbers -ZW
, -DATA
are fitted with Zoneworks communications modules
(nodes). These fittings are monitored using either Powerline Carrier Technology that utilises the
power cable to provide data communication or a dedicated data cable to/from data routers installed
on a dedicated data trunk connected to a central Server (can also be connected via
Ethernet/Internet/Fibre). Zoneworks software on the server is used to monitor, coordinate testing and
collate test data from each Ultrablade and can be commissioned by a single push of the test switch,
or scanning of the supplied barcode. The LED Test Switch indicator provides a multifunction indication
of the status of the Ultrablade during testing and normal operation:
State
LED Operation
Commissioned
LED on Solid (Green)
Un-commissioned
LED flashes at 0.5Hz (0.5s Green, 0.5s Yellow)
Emergency Light Test In Progress
LED flashes at 3s On (Yellow) & 0.5s Off
In the case of the DATA version a 2-
way “figure 8” cable and terminal block facilitates the
connection to the DATA network via a multi-drop bus (daisy chain connection). For further
information of installation of a Zoneworks LW system, please refer to the Zoneworks Users Guide
and Commissioning Guide (incl. DATA version)
DALI EM Option
Ultrablades with part numbers
-DALI
are fitted with DALI modules (nodes) that facilitate connection
and integration to 3
rd
Party Lighting Control Systems. Before installing the
–DALI fitting please
confirm that the Lighting Control System has the capability to monitor DALI Emergency Luminaires.
The
–DALI fitting will be addressed and configured into the control system by the Lighting Control
System Commissioning Technicians and not Clevertronics.
State
LED Operation
Commissioned/ Un-commissioned
LED on Solid (Green)
Emergency Light Test in progress
LED flashes at 1s On (Yellow) & 1s Off
“IDENTIFY COMMAND”
Fitting goes into emergency mode for 10 seconds
A 2-
way “figure 8” cable and terminal block facilitates the connection to the DALI network. DALI
connections are marked as Da Da.
Networking:
When installing the L10 Ultrablade PRO on a monitored network, (
ZONEWORKS, DATA, DALI
) simply
insert the relevant Smart Node PCA.
Installation:
The L10 Ultrablade Pro Surface Mount LED Exit (LUBPRO-SM) is a surface mount fitting. The LUBPRO-
SM can be attached directly to any solid surface. Please follow the steps below to install the LUBPRO Exit:
•
Open the fitting using the 2 screws on either side of the blade.
•
Locate the mounting surface.
•
Drill holes in the mounting base to suit the mounting method, Ceiling or Wall (see images below).
•
Use the mounting bracket to mark-out the mounting holes for Ceiling or Wall Mount.
•
Drill power access hole as required.
•
Mount the fitting using appropriate fixings.
•
Route the power to the mains connection and connect the 240VAC supply.
•
Attach the blade assembly to the bracket and tighten the 2 mounting screws.
•
Apply power to the fitting and test.
•
If the CTP capabilities are activated, please affix the CTP Status Label to a visible surface.
Changing EXIT Legend Inserts
:
The Ultrablade Pro Exit comes with an assortment of standard legends.
1.
To remove the legend, grasp the centre of the bottom trim piece and pull down slightly to expose
the legend edge. See photo.
2.
Grasp the bottom edge of the legend and slide the existing legend out of the blade, while working
the edges out along the sides.
3.
Slide the new legend into the blade, ensuring to fit the edges into the sides then slide the legend to
the top of the blade. Insert one bottom corner then the other. Slide the legend down into the
bottom trim.