WARNING
INJURY TO PERSONNEL AND EQUIPMENT DAMAGE may result
from an improper drain connection.
Installation Checks
Proper operation of the Cleveland Convection PRO XVI steamer is dependent upon
proper installation. After the steamer has been installed, a few quick checks could save
unnecessary service calls.
1.
The unit must be level
2.
The Convection Pro XVI steamer requires a cold Water connection for proper, efficient
operation. DO
NOT USE HOT WATER. The cold water must be connected to the line strainer,
located at the front
lower-right of the steamer base.
3.
Check that the manual water supply valve is open.
4.
Check all water supply lines and valves for leaks.
5.
Check that the water supply pressure and Water quality meet the requirements of installation
paragraph.
6.
On electric units, verify that the supply voltage meets the voltage requirements on the rating
plate
inside the base cabinet, and the voltage shown on the packing slip. Verify that the unit is
protected
with a separate fused disconnect, and is properly grounded in accordance with the
National Electric
Code.
7.
On gas, steam coil, and direct-steam-connected units, verify that there is a 115 Volt connection
at the
handi-box located on the left side of the base at the bottom front.
8.
On steam coil units, the incoming steam pressure must be 35 to 50 psi. Less than 35 psi will not
effectively operate the unit. Pressure in excess of 50 psi must be reduced (with a pressure
reducing
valve) to 35 to 50 psi.
9. Check that the drain lines meet the installation requirements specified in installation paragraph.
10. After completing checks 1 through 9, and correcting any deficiencies. refer to the Start-up and
Preheat
instructions in the Operation section. Verify that the unit operates properly, and make checks
11 and 12.
11. Check to ensure that the water in the boiler sight gage glass automatically stays about 1/3 full
when the
boiler is started up and operated.
12. Check to ensure that the steam pressure gage registers 10psi. The steam pressure is factory-
adjusted
to provide the proper pressure. In some cases, however, the factory setting may shift due to
shaking in
transit, and resetting will be required after installation. Proper adjustments and
maintenance
procedures
are detailed on separate data sheet entitled "Steam Pressure Adjustments.
Adjustments
should be made
only by qualified service personnel. The factory pressure settings shown
in the
accompanying chart should
never be exceeded.