4. Installation Instructions 

4.1 Klip-lok Interface Installation 

According your plan, mark 
the position of Klip-lok 
Interface on the tin roof with 
Marker Pen and String. 
Place Klip-lok Interface on 
the marked position, as 
shown figures on the right.

 

 

       

 

4.2 Rail Installation

 

4.2.1 
To connect multiple rails 
together, slide half of splices 
on the rear side of the 
pre-assembled rails. Fasten 
the first M8 Allen bolt firmly 
using the Allen key. Now 
slide the next rail segment 
into the other half of splice. 
4.2.2 
Tighten the second M8 
Allen bolt using the Allen 
key. The connection is 
finished. An expansion gap 
at the rail joints is 
recommended. For this 
purpose, leave a gap about 
the same width as a finger 

 

 

Summary of Contents for V-ezRack SolarRoof

Page 1: ...uoju Hi tech Ind Dev Zone Xiang an District 361101 Xiamen Fujian China E sales clenergy com cn W www clenergy com cn Tel 86 592 311 0088 SHA 603628 PV ezRack SolarRoof Klip Lok Interface with B50 Rail...

Page 2: ...installer is solely responsible for Complying with all applicable local or national building codes including any updates that may supersede this manual Ensuring that PV ezRack and other products are...

Page 3: ...Driver Torque Wrench Allen Key 6mm for M8 Hexagon Socket Screw Tape String Note The tools in the figure are only used for installation of rack system not included in supply scope please consult syste...

Page 4: ...lenergy com cn Tel 86 592 311 0088 SHA 603628 ER I 13 TH Klip lok Interface for Hidden 26 ER I 16 TH Klip lok interface for Standing seam 22 ER I 18 TH Interface for Standing Seam 20 ER I 20A TH Klip...

Page 5: ...Zone Xiang an District 361101 Xiamen Fujian China E sales clenergy com cn W www clenergy com cn Tel 86 592 311 0088 SHA 603628 3 System Overview 3 1 Overview of PV ezRack SolarRoof End Clamp U18 Inter...

Page 6: ...y to maintain the required torque 3 Professional tools and tool belts are recommended 4 In some cases fasteners could be seized over time As an option if want to avoid galling or seizing of thread app...

Page 7: ...String Place Klip lok Interface on the marked position as shown figures on the right 4 2 Rail Installation 4 2 1 To connect multiple rails together slide half of splices on the rear side of the pre as...

Page 8: ...SHA 603628 between the rail joints and then loosely tighten the M8 Allen bolt Note Skip this step if the rail is long enough and no need to splice 4 2 3 Affix the Rails and Klip lok Interface by Rail...

Page 9: ...n 4 3 1 According to your plan install all Rails 4 3 2 Mark the position of PV Module on Rails with Marker Pen Stretch a String as a reference to align PV Module Place the first PV Module on the marke...

Page 10: ...Tel 86 592 311 0088 SHA 603628 4 3 4 To buckle to Clamps with Z module put one leg of Z module into the channel of the Rail first then press second leg of Z module into the channel 4 3 5 Buckle the I...

Page 11: ...ce parallel to the stretched String and fasten the Inter Clamp Note Pay attention not to touch the stretched String when placing the PV Modules Recommend torque of M8 bolt is 13N m 4 3 7 Following the...

Reviews: