Place the second PV
Module, with its side face
parallel to the stretched
String, and fasten the Inter
Clamp.
Note:
Pay attention not to touch
the stretched String when
placing the PV Modules
Recommend torque of M8
bolt is 13N.m
4.3.7
Following the above steps
to install other PV-Modules
of this line and fasten the
End Clamp at another side
of end.
4.3.8
Repeat above steps to
install the rest PV-Modules.
The distance of any
adjacent face of PV-Module
should be 20mm.