Installation Instruction
4. Installation Instruction
4.1 Pipe Installation
Dig a hole with the diameter of 300 mm.
Place the pole into the middle of the hole and fill it
with concrete (min 25 MPa strength). Maintain the
position of the post. The allowed vertical tolerance
is ±2°.Keep the axle of the 2- Ø16 holes parallel to
East-West;keep the vertical angle deviation within
±5°.For more than one system on one site maintain
all the axles of 2- Ø16 holes aligned.
4.2 Steel Cap Installation
Connect the Pipe to the corrugated washer and Steel Cap Assembly with M14*150 hexagonal
bolt, plain washer 14, spring washer 14, M14 nut .
Combine two Steel Caps with M14*110 hexagonal bolt, plain washer 14, spring washer 14,
M14 hex nut.
Note
:
1. Do not fasten the Bolt prior to complete the assembly of PM-A Rectangular Tube-Master.
2. Keep all the Bolt head aligned.